Provisional General Fund Revenue and Capital Outturn 2024/25

June 24, 2025 Cabinet (Cabinet collective) Awaiting outcome View on council website
Full council record
Purpose

The report outlines the General Fund Revenue
and Capital outturn for the financial year 2024/25 and summarises
the Reserve balances as at 31 March
2025. It also considers the General Fund Revenue outturn for
2024/25 and to approve the Revenue and Capital Budget carry
forwards. The report also provides a statement of the year-end
financial position and progress with approved capital investment
projects.
 

Content

Cabinet has considered and reviewed the report and
appendices as presented and:

 

General Fund (GF): Revenue

 

(a) Noted the provisional General Fund revenue
outturn for 2024/25, as summarised at Appendix A.

(b) Noted the key factors which have led to the
underspend in the provisional 2024/25 General Fund Revenue outturn,
noting the explanations provided for the variances compared to the
revised 2024/25 revenue budget.

(c) Approved the carry forwards of £20,540 in
relation to General Fund revenue projects which were not undertaken
during the year as planned.

 

GF: Review of Reserves

 

(d) Noted the estimated balance of Reserves of
£35.315 million as at 31 March
2025.

 

GF: Capital

 

(e) Noted the 2024/25 General Fund Capital
provisional outturn of £27.707 million.

(f)   Noted the General
Fund Capital Programme schemes as shown in Appendix B.

(g) Approved the carry forwards of £8.164
million in relation to General Fund capital projects due mainly to
slippage.

(h)  Noted that a full
review of the Capital Programme will be submitted to Cabinet at its
December 2025 meeting to include re-phasing of the existing
programme and new Capital bids for the next budget
cycle.

Related Meeting

Cabinet - Tuesday, 24 June 2025 10.00 a.m. on June 24, 2025

Supporting Documents

GF Outturn Summary 2024-25.pdf
General Fund Outturn 2024-25.pdf
Appendix B - GF Capital Outturn 2024-25.pdf

Details

OutcomeFor Determination
Decision date24 Jun 2025
Effective from3 Jul 2025
Subject to call-inYes