2023/24 Provisional General Fund Revenue and Capital Outturn
June 25, 2024 Cabinet (Cabinet collective) Approved View on council websiteFull council record
Content
Cabinet agreed
to
(a)
Acknowledge the 2023/24 general fund revenue outturn
position and the net underspend (after income from Taxation and
Government Grants) in the year of £0.168 million as
summarised in Appendix A, and the explanations provided for the
variances compared to the revised 2023/24 revenue
budget;
(b)
Acknowledge the consequent increase in the General
Fund as at 31 March 2024 of £2.064m to around
£20.1m;
(c)
Approve the carry forwards of £0.061 million
in relation to General Fund revenue projects which were not
undertaken during the year as planned.
(d)
In relation to the Capital Programme:
(i) Note the
2023/24 capital outturn of £10.782 million.
(ii) Acknowledge
the performance achieved in relation to the Capital Programme
schemes substantially completed in 2023/2024, summarised in
Appendix B.
(iii) Approve
the carry forwards of £1.819 million in relation to General
Fund capital projects due mainly to slippage.
(iv) To note
that a full review of the Capital Programme will be submitted to
Cabinet at its December 2024 meeting to include re-phasing of the
existing programme and new Capital bids for the next budget
cycle.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 25 Jun 2024 |
| Subject to call-in | Yes |