2023/24 Provisional Housing Revenue Account (HRA) and Capital Outturn

June 25, 2024 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...it acknowledged the 2023/24 Housing Revenue Account (HRA) revenue underspend of £0.511 million, the increased HRA balance of £3.007 million, the capital outturn of £56.622 million, the performance of completed capital projects, and approved carrying forward £16.2 million for HRA housebuilding and £0.339 million for capitalised repairs to 2024/25.

Full council record
Content

Cabinet agreed
to
 
(a)     
Acknowledge the 2023/24 revenue outturn position and
the net underspend in the year of £0.511 million, and the
explanations provided for the variances compared to the revised
2023/24 revenue budget.
 
(b)     
Acknowledge the overall increase in the Housing
Revenue Account balance as at 31 March
2024 to £3.007 million.

 
(c)     
In relation to the Capital Programme:

 

(i) Note the 2023/24 capital outturn of £56.622
million.

 
(ii)  Acknowledge the performance achieved
in relation to the Capital Programme schemes substantially
completed in 2023/24, summarised in Appendix A.

 
(iii) Approve
the carry forward amounts of £16.2 million to 2024/25 in
relation to HRA housebuilding during 2023/24, due to slippage and
£0.339 million for capitalised repairs.

Supporting Documents

Appendix A - HRA Capital Programme Performance 2023-24.pdf
2023-24 Provisional HRA and Capital Outturn.pdf

Details

OutcomeRecommendations Approved
Decision date25 Jun 2024
Subject to call-inYes