Delta and Depot West Trackwork Renewal – Increase in Approved Spend

March 31, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved spending up to £1,150,000.00 with the Supplier on 31/03/2026. This decision increased the previously approved spend by £150,000.00. The decision included the provision of plain-line rail and Under Bearer Pads.

Full council record

Purpose

Approval to spend £1,000,000.00 on new Switches & Crossings trackwork was provided on 27 June 2025.
Several unforeseen changes to Scope have occurred as part of design refinement, with the two highest value being:

• Requirement for provision of plain-line rail through PS10-PS11, with the ordered S&C unit to be saved for redeployment at a more strategically-useful location. Cost approx. £40,831.62.

• Requirement for Under Bearer Pads (UBPs) to protect ballast from increased forces associated with the concrete bearers and sleepers. Cost approx. £100,000.

These unforeseen changes to Scope mean Supplier costs will exceed the original £1m approval limit.

The purpose of this report is to seek approval to increase spend with the Supplier up to a value of £1,150,000.00 (an increase of £150,000.00 upon previous approval).

Decision

Approve spend of up to £1,150,000.00 with the Supplier (an increase of £150,000.00 upon previous approval).

Alternative options considered

• Approve spend of up to £1,150,000.00 with the Supplier (an increase of £150,000.00 upon previous approval).

• Refuse additional spend. To keep cost below the already approved £1,000,000.00 spend, Under Bearer Pads would not be included as part of the manufactured trackwork. Without UBPs, a full ballast renewal would be required, rather than the planned partial renewal / skim dig. This would cost an estimated £450,000.00 in
additional Contractor fees.

Supporting Documents

Delta and Depot Increased Spend.pdf

Details

OutcomeRecommendations Approved
Decision date31 Mar 2026