T002 A61 Wakefield Road Corridor change control
June 11, 2026 Section 73 Officer (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Section 73 Officer approved the T002 A61 Wakefield Road Corridor change control on 11/06/2026. The decision approved an additional £2.1m from within the SYMCA portfolio, an end date extension to January 2027, and a reprofile of outputs and outcomes.
Full council record
Purpose
In March 2022 full approval was secured for the project.
The four local authorities and the MCA each hold a portfolio of projects within their TCF/CRSTS programmes and in September 2025 the MCA approved the continuation of the flexibility previously approved on the TCF programme to enable the movement of funds between schemes within their portfolios when necessary to enable delivery whilst ensuring minimal impact on the programme outputs and outcomes.
In June 2026, the Change Control Panel recommended approval of:
- An additional £2.1m from within the SYMCA portfolio (Thorne)
- End date extension to January 2027
- Reprofile of outputs and outcomes to align
Decision
Option 1 – Approve the recommendation
Alternative options considered
1. Approve the recommendation
2. Reject the recommendation
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Jun 2026 |