ZEBRA project delivery delay – extension of compensation agreement

June 15, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the payment of £123,500 in compensation to a bus operator. This decision was made on 15/06/2026 to cover additional running costs incurred due to delays in fitting Pantograph infrastructure. The compensation covers the period between April 2025 and July 2026.

Full council record

Purpose

Due to the delays in the project to fit the Rotherham Transport Interchange Pantograph infrastructure supplied via the DfT Zero Emission Bus Regional Areas (ZEBRA) funding, the local bus operator has had additional costs generated by the allocated buses having to return to the depot for a top up charge during the duty cycles. This compensation agreement covers the additional costs incurred by the operator between April 2025-July 2026 totalling £123,500.

The final work will conclude in July 2026 with a go live date of August 2026

Decision


Previous delays have already generated agreed compensation to allow services to continue to run and mitigate any impact on customers. With the project ending in August 2026 it is highly likely that this will be the last compensation payment made. SYMCA will pay the operator £123,500 in compensation to cover additional running costs incurred because of the delay in fitting the Pantograph infrastructure.

Alternative options considered

Option 1 do nothing brings reputational damage between SYMCA and the Bus Operator, DfT, partners and the public resulting in the Operator reverting to using diesel buses or reduce services.

Option 2 do something pay the compensation payment.

Option 3 Do most approve a dedicated revenue funding stream to mitigate the impact of delays on capital project delivery, this could be a learning point for future projects.