A change control on Arup’s existing Meadowhall P&R Expansion appointment to cover Compensation Events 03 and 05, as outlined in the associated POB approval paper.

September 8, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Executive Director of Transport approved a change control on Arup’s Meadowhall P&R Expansion appointment on 08/09/2026. This approval covers Compensation Events 03 and 05, increasing Arup's fee by £126,451.86. The decision includes approving the increase in Arup’s fee by £126,451.86.

Full council record

Purpose

CE05 details a proposal from Arup to undertake a Monitoring and Evaluation (M&E) Plan - a requirement for the OBC/FBC. This was not specified in the original scope for Arup’s appointment. The SYMCA Project Manager asked Arup to price for this aspect due to resource capacity constraints. CE05 is priced at £9,696.33. Undertaking the necessary project monitoring and evaluation activity sits outside of this appointment and will need to be accommodated within the overall project cost plan and could be procured outside of Arup’s appointment.

CE03 details a proposed overarching CE covering 17 separate elements where additional work is required by Arup resulting in a fee increase. The majority of this relates to the additional work arising because of the change from a single deck solution to a Multi Storey Car Park. This CE03 is priced at £116,755.53.

The total CE amount for which approval is sought is therefore £9,696.33 plus £116,755.53 = £126,451.86. This would take Arup’s total contract value to £430,454.88, which is 47.25% above the original total.
 

Decision

Option 1: Approve

Alternative options considered

Option 1: Approve the increase in Arup’s fee by £126,451.86
Option 2: Do not approve
 

Details

OutcomeRecommendations Approved
Decision date8 Sep 2026