Anchor Bay and Pier Stem Phases 3 and 4 - Southend Pier

August 6, 2025 Cabinet Member for Finance, Assets and Public Transport (Cabinet member) Key decision Approved View on council website
Full council record
Purpose

The Council has undertaken a
review of options to take forward essential outstanding structural
works to Southend pier following the Liquidation of the appointed
Contractor. The recommended approach is to enter into a Contract
for the remainder of the current Contract Period (12
months).

Content

That UKI Mechanical Limited be directly
awarded the contract to complete structural works to the Southend
pier stem (Anchor Bay Phases Three and Four).

Reasons for the decision

To put in place a main
contractor to complete Phases Three and Four of the Pier Stem
Anchor Bay Structural programme.
 
A decision is required as a
matter of urgency to ensure that works can continue promptly once
the school summer holiday period has finished. A programme delay
would compromise the ability to complete structural works during
the less busy Autumn and winter seasons.

Alternative options considered

The Council considered other
procurement route options including use of an existing Framework or
an retender process. However, this would delay works and would be
highly likely to result in increased tender prices.

Supporting Documents

Report - Anchor Bay Pier Stem Phases 3 4.pdf

Details

OutcomeRecommendations Approved
Decision date6 Aug 2025
Subject to call-inYes