DRAFT GENERAL FUND CAPITAL STRATEGY 2025/26 TO 2029/30
January 14, 2026 Approved View on council websiteFull council record
Content
Council considered a report relating to
revisions to the 2025/26 Capital Programme and Strategy and
requesting approval to the draft 2026/27 Capital Programme for
consideration by the Overview & Scrutiny Committee.
The Portfolio Holder for Resources and
Performance advised that the investments detailed in the report
would deliver asset renewal and enhancements such as
£1.8Million for fleet replacements, £535K for Stevenage
Arts and Leisure Centre upgrades, £1Million to repurpose the
sports hall, and £500K for Ridlins track renewal.
There were also additional allocations including £490K for
green space improvements and £650K for a deferred works
reserve to manage urgent asset needs.
The following comments were made:
·
Reassurance was given that the existing Sports and Leisure Centre
would have a life of at least 10 years and that the Gordon Craig
Theatre would also continue with improvements to the infrastructure
of the Theatre;
·
The additional funding for the Council’s environmental work
was welcomed including renewing parks and green spaces for the
enjoyment of all communities;
·
The impact of the changes referred to on the youngest people in the
town was a positive step forward in future planning and making the
town better for future generations;
·
Stevenage was a dementia and age friendly accredited town and the budget would enable more resources for
all activities such as the dementia festival;
·
The work of the cross party
Council’s Financial Security Group (CFSG) was acknowledged in
the Budget process.
It was RESOLVED:
1.
That the General Fund growth bids identified for inclusion in the
Capital Strategy (section 4.2, and Appendix A to the report) be
approved in principle, including the proposed budget level in the
deferred works reserve budget of £650K.
2.
That the virements in paragraph 4.3.5 of the report be
approved.
3.
That the work of the Council’s Financial Security Group
(CFSG) in reviewing all General Fund capital bids prior to
inclusion in the final 2026/27 Capital Strategy to the February
2026 Cabinet be noted.
4.
Draft General Fund Capital Budget for 2025/26 to 2029/30 of
£117Million, as set out in Appendix B to the report, be
included into the Council’s budget setting processes for
consideration by the Overview & Scrutiny Committee.
5.
That the approach to resourcing the General Fund capital programme
as outlined in the report (Paragraph 4.4) be approved.
6.
That the revenue contribution to capital, 2026/27 to 2028/29 as set
out in table 2, paragraph 4.2.1 be included into the
Council’s budget setting processes for consideration by the
Overview & Scrutiny Committee.
7.
That the approved revenue surplus in any year of up to £500K
that can be allocated to the capital reserve to support capital
expenditure be noted.
8.
That the proposed use of Community Infrastructure Levy (CIL), and
Biodiversity Net Gain (BNG) contributions as set out in section 4.6
be included into the Council’s budget setting processes for
consideration by the Overview & Scrutiny Committee.
9.
That the legal implications of Section 24 of the Local Government
and Public Involvement in Health Act 2007 in relation to financial
decisions (capital) made by a council that is due to be abolished
or reorganised in section 5.2 be noted.
Related Meeting
Cabinet - Wednesday, 14 January 2026 2.00pm on January 14, 2026
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 14 Jan 2026 |