Bus Pinch Points – Compstall Road Zebra Crossing Traffic Regulation Orders (TROs)

July 22, 2026 Cabinet Member for Parks, Highways & Transport Services (Cabinet member) Approved View on council website
Full council record

Decision

The Cabinet Member for Parks, Highways & Transport Services has given approval to the following recommendations:

(1)  To continue with the previous decision made on 22nd October 2024 to proceed with the Bus Pinch Points – Compstall Road Zebra Crossing scheme, with the inclusion of an additional disabled parking bay on Cote Green Lane, as shown on Drawing F-0700 007-10 Rev B within Appendix E.

(2)  That approval be given to the amended TROs associated with the Bus Pinch Points – Compstall Road Zebra Crossing scheme and that the orders be made as set out within the revised schedule which was included as Appendix A to the report submitted to the Marple Area Committee on 11th March 2026.

A public question from a resident was submitted in relation to the proposed Zebra Crossing at the Marple Area Committee on 11th March 2026. The details of the question and associated response included within the minutes from the meeting, copy of the Stage 1 Road Safety Audit and associated Designer’s Response and the drawing of the Visibility Splays were considered by the Cabinet Member in making the decision to approve the scheme. These are included as Appendices A-C to this decision record.

Alternative options considered

A number of alternative locations for the Zebra Crossing, and associated waiting restrictions, were considered during development of the design. Further information is included within the report submitted to the Marple Area Committee in July 2024.
The alternative to the proposals laid out in this report is to continue with the current layout and not derive the benefits to active travel and bus stop access that the scheme would provide.

Supporting Documents

Appendix B - Stage 1 RSA and Response_Redacted.pdf
Bus Pinch Point Scheme Proposed Highway Improvements Compstall Road Marple Bridge Traffic Reg.pdf
Appendix D - Printed decision 22 Oct 2024.pdf
Appendix C - Visbility Splay F-0700-007-011 D.pdf
Appendix A - Marple AC Minutes 11 March 2026.pdf
Appendix E - Executive Decision Record - Drawing F-0700-007-010.pdf

Details

OutcomeRecommendations Approved
Decision date22 Jul 2026
Effective from2 Sep 2026
Subject to call-inYes