Hattersley Annual Update April 2024 to March 2025

April 23, 2025 Executive Cabinet (Other) Key decision Approved View on council website
Full council record
Purpose

The report provided an update on the
Hattersley Regeneration Programme for the period 2024/2025

Content

That Executive Cabinet:
(i)            
Note the work undertaken in 2024/2025 as part of the Hattersley
Regeneration Programme and the proposed next steps.
(ii)           
Approve the payments to Onward Homes, Homes England and the
Council, to reimburse expenditure as set out in table 5 (section
4) with the sum of up to £0.011m to finance public realm
schemes and a sum of up to £0.037m to finance collaboration
agreement expenditure.  The expenditure
is to be financed via the balance held by the Council for the
Hattersley Land Board, the total of which is included in table 2
and was £4.487m as at 1 April
2024.
(iii)          
Approve the transfer of £0.600m to Onward Homes for the
long term stewardship of the public
realm as set out in section 3.6. The expenditure is to be
financed via the balance held by the Council for the Hattersley