Capital Monitoring P3 2025-26

August 27, 2025 Executive Cabinet (Other) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve the 2025/26 capital monitoring report at Period 3, including a revised budget of £57.646m, a reprofiling of £26.677m of capital spend into 2026/27, and other capital changes of £11.597m, resulting in a projected spend of £56.863m for 2025/26.

Full council record
Content

RESOLVED
That Executive Cabinet approve:

(i)              
The opening scheme budget for 2025/26 of £95.920m, as
summarised in Table 1;

(ii)            
The reprofiling of £26.677m of capital spend for 2025/26
into 2026/27, as outlined in Appendix 1;

(iii)          
Other capital changes of £11.597m, as summarised in Table
3 and Appendix 2;

(iv)          
The revised 2025/26 budget at Period 3 of £57.646m, as
summarised in Table 3;

(v)            
The capital programme position of projected spend of
£56.863m for 2025/26, following Cabinet approval to reprofile
project spend of £26.677m into 2026/27.

Supporting Documents

Appendix 2 - Change Requests.pdf
Appendix 1 - Reprofiling Requests.pdf
Capital Monitoring Report P3 2025-26.pdf
Appendix 3 - Service Area Capital Milestones.pdf

Details

OutcomeRecommendations Approved
Decision date27 Aug 2025
Subject to call-inYes