Stalybridge Public Realm Delivery

December 17, 2025 Executive Cabinet (Other) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve the detailed design for the Stalybridge Public Realm priority projects, delegate decision-making authority for their implementation to the Strategic Growth Director, and approve progressing design work on the Stalybridge War Memorial.

Full council record
Purpose

This report
sought approval for the delivery of the public realm works for the
six priority projects in Stalybridge using secured Capital
Regeneration Projects funding. The report also provided
 an update on the
potential to secure additional City Region Sustainable Transport
Settlement (CRSTS) funding for public realm and sought approval to
progress design work in relation to the Stalybridge War
Memorial.

Content

RESOLVED

(i)                
To approve the
detailed design for the Stalybridge Public Realm priority
projects.

(ii)              
Subject to
recommendation 1, delegate decision making authority for
implementation of the priority public realm projects as part of the
Stalybridge Regeneration Programme to the Strategic Growth
Director, in consultation with the Strategic Director of Housing,
Environment & Estates, the Executive Member for Growth, Housing
and Homelessness and Executive Member for Town Centres and
Connectivity, the S.151 Officer, and Monitoring Officer as
appropriate.

(iii)            
To give approval
to progress design work on the Stalybridge War Memorial, including
delegating decision-making authority for detailed design, necessary
public consultation and related procurement, to the Strategic
Growth Director, in consultation with the Strategic Director of
Housing, Environment & Estates, the S.151 Officer, and
Monitoring Officer as appropriate.

(iv)            
Note that a
further report will be brought to Executive Cabinet on completion
of the design works for the War Memorial to seek any required
approval for delivery 

Alternative options considered

The Stalybridge Public Strategy had
considered a number of design options for the priority project
areas in accordance with the external grant funding
conditions.

Related Meeting

Executive Cabinet - Wednesday, 17th December, 2025 1.00 pm on December 17, 2025

Supporting Documents

Stalybridge Public Realm Delivery.pdf
Appendix. 1 for Stalybridge Public Realm Delivery.pdf

Details

OutcomeRecommendations Approved
Decision date17 Dec 2025
Subject to call-inYes