2026/27 CAPITAL BUDGET - QUARTER 1 FORECAST OUTTURN

July 29, 2026 Executive Cabinet (Other) Key decision In call-in window View on council website
Full council record

Purpose

This report provides Executive Cabinet with the forecast outturnposition in relation to the capital budget for 2026/27 at Period 3

Decision

RESOLVED

(i)                That Approval be given to the reprofiling of £32.312m of capital budget from 2026/27 into 2027/28, as detailed in Appendix 1.

(ii)              That Approval be given to other capital changes as summarised in Appendix 2.

(iii)            The revised 2026/27 approved scheme budget at Period 3 of £79.414m, as summarised in Table 2 be Approved.

(iv)            The Grant Funding agreement of £0.512m with Corpus Christi Academy trust to enable the school to carry out the scheme at All Saints Academy be Approved.

(v)              A location change of the satellite from Quantum Point,2 Gregory Street, Hyde, SK14 4HR, to Cromwell High School/Rayner Stephens site 

Supporting Documents

Appendix 1 Re-profiling Requests.pdf
Appendix 3a- Strategic Growth Unit.pdf
Appendix 2 Change Requests.pdf
Appendix 3d- Adults Milestone.pdf
Appendix 3e- Digital Tameside.pdf
202627 CAPITAL BUDGET - QUARTER 1 FORECAST OUTTURN.pdf
Appendix 3b- Housing Environment Estates.pdf
Appendix 3c- Childrens Milestone.pdf

Details

OutcomeRecommendations Approved (subject to call-in)
Decision date29 Jul 2026
Expected date29 Jul 2026
Originally due29 Jul 2026
Subject to call-inYes