2026/27 CAPITAL BUDGET - QUARTER 1 FORECAST OUTTURN

July 29, 2026 Executive Cabinet (Other) Key decision Approved View on council website
Full council record

Purpose

This report provides Executive Cabinet with the forecast outturnposition in relation to the capital budget for 2026/27 at Period 3

Decision

RESOLVED

(i)                That Approval be given to the reprofiling of £32.312m of capital budget from 2026/27 into 2027/28, as detailed in Appendix 1.

(ii)              That Approval be given to other capital changes as summarised in Appendix 2.

(iii)            The revised 2026/27 approved scheme budget at Period 3 of £79.414m, as summarised in Table 2 be Approved.

(iv)            The Grant Funding agreement of £0.512m with Corpus Christi Academy trust to enable the school to carry out the scheme at All Saints Academy be Approved.

(v)              A location change of the satellite from Quantum Point,2 Gregory Street, Hyde, SK14 4HR, to Cromwell High School/Rayner Stephens site 

Supporting Documents

Appendix 1 Re-profiling Requests.pdf
Appendix 3a- Strategic Growth Unit.pdf
Appendix 2 Change Requests.pdf
Appendix 3d- Adults Milestone.pdf
Appendix 3e- Digital Tameside.pdf
202627 CAPITAL BUDGET - QUARTER 1 FORECAST OUTTURN.pdf
Appendix 3b- Housing Environment Estates.pdf
Appendix 3c- Childrens Milestone.pdf

Details

OutcomeRecommendations Approved
Decision date29 Jul 2026
Effective from7 Aug 2026
Expected date29 Jul 2026
Originally due29 Jul 2026
Subject to call-inYes