Medium Value Variation at Samuel Laycock Academy – Building Services Lifecycle Works

July 17, 2024 Strategic Director of Housing, Environment and Estates (Officer) Approved View on council website
Full council record
Purpose

The Council will follow the Medium Value
Variation prescribed in the Facilities Management Contract to
approve the delivery of lifecycle repairs and replacement to the
building systems which have been identified by an independent
dilapidation survey.
The project will be funded by the Local Authority through the
Lifecycle reserve held for Samuel Laycock within the affordability
account.

Content

That it be DETERMINED that:

The Council will
follow the Medium Value Variation process prescribed in the
Facilities Management Contract to approve building system lifecycle
repairs at the Samuel Laycock school.
The project will
be funded by the Local Authority through the Lifecycle reserve held
for Samuel Laycock within the affordability account.

Supporting Documents

Appendix 1.pdf
Decision Notice.pdf

Details

OutcomeRecommendations Approved
Decision date17 Jul 2024