Cabinet Members' Items - Report of the Economic Growth, Regeneration & Tourism Portfolio Holder - A.4 - Sunspot Workspace, Jaywick Sands - Post Project Review
April 11, 2025 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council websiteFull council record
Content
RESOLVED that
Cabinet –
a)
endorses this post project and operational review of
the Sunspot, Jaywick Sands, which highlights the success of the
workspace since opening in September 2023, the challenges in
construction, and the lessons learnt for future regeneration
projects; and
b)
in respect of the additional costs of potentially up
to £100,000 that have emerged from the project’s final
account processes, agrees that this be funded by a transfer within
the existing HRA Capital Programme / wider HRA revenue budgets as
part of finalising the overall HRA outturn position for
2024/25.