NATIONAL GRID ELECTRICITY DISTRIBUTION WAYLEAVE AGREEMENT – LAND (PLAYGROUND & FOOTBALL GROUND) OFF ALEXANDRA ROAD, SEBASTOPOL, PONTYPOOL, TORFAEN

November 22, 2023 Deputy Chief Executive (Resources) (Officer) Key decision Approved View on council website
Full council record
Content

That the Group Leader Asset Management
approves that Torfaen County Borough Council enters into a wayleave
agreement with National Grid Electricity Distribution for the
installation and maintenance of an underground 11KV cable through
Council owned land (Playground & Football Ground) situated off
Alexandra Road, Sebastopol, Pontypool, as per the terms contained
in this report.

Reasons for the decision

As contained within Report.

Alternative options considered

As contained within Report.

Supporting Documents

NATIONAL GRID ELECTRICITY DISTRIBUTION WAYLEAVE AGREEMENT LAND PLAYGROUND FOOTBALL GROUND OFF .pdf

Details

OutcomeRecommendations Approved