...to approve new loan facilities for Aspire (CRP) Limited, totaling up to £7,600,000, to fund the refurbishment of Building 900 and the completion of Building 800 at Chesterford Research Park, subject to Full Council approval and noting the implications on the Council's access to the Public Works Loan Board.

Full council record
Purpose

To consider the report regarding a request for
further investment at Chesterford Research Park.

Content

RESOLVED to:
 
I.              
approve a new loan facility of up to
£5,100,000 be made available to Aspire (CRP) Limited, for the
refurbishment of Building 900 at an interest rate of 6.25% on a
repayment basis, to be drawn down in tranches over a period of up
to 2 years with repayments commencing from 1 April 2027, subject to
Full Council agreeing to make funding available for this
purpose;
II.            
approve a new loan facility of up to
£2,500,000, be made available to Aspire (CRP) Limited, for
the completion of Building 800 at an interest rate of 6.25% on an
interest only basis, to be drawn down in tranches over a period of
up to 2 years with repayments commencing from 1 April 2026, subject
to Full Council agreeing to make funding available for this
purpose;
III.          
note the implications of making the loan on the
Council’s access to Public Works Loan Board, as set out in
paragraphs 24 to 26 of the following report.

Supporting Documents

Aspire Request cabinet report August 2025.pdf
Appendix B - Loan request letter from Aspire requesting 21.06m.pdf
Aspire Request council report August 2025.pdf
Appendix C - Council report additional funding for further development at Chesterford Research.pdf
Appendix A - Loan request letter from Aspire requesting additional B800 and B900 funding.pdf

Details

OutcomeRecommendations Approved