Cranleigh Leisure Centre New Build
October 3, 2023 Executive (Other) Key decision Unknown View on council websiteFull council record
Purpose
To approve the updated scope and budget of the
project, proceed with construction contract and relevant
delegations to officers.
Content
I.
That a revised capital budget of
£31,137,252, as shown in the financial viability assessment
at Exempt Annexe 1, be agreed to deliver a new-build Cranleigh
Leisure Centre;
II.
That the leisure centre is built to Passivhaus
certification standards;
III.
That authority be delegated to the Joint Director
for Place, in consultation with the relevant portfolio holder, to
submit a planning application in respect of the proposed new
build;
IV.
That authority be delegated to the Joint Director
for Transformation and Governance, in consultation with the
relevant portfolio holder, to conduct the procurement of a
contractor for the build and all related professional services,
including, but not limited to, the Employers Agent and Design
team;
V.
That authority be delegated to the Joint
Executive Head of Legal and Democratic Services to complete and
execute all necessary contractual documents.
Supporting Documents
Details
| Outcome | Recommmend Forward to Council |
| Decision date | 3 Oct 2023 |
| Subject to call-in | Yes |