Executive RESOLVED to approve:
 

      
I.         
A Supplementary Budget of £223,298 for the
purposes of progressing Weydown Road
Community Hub Option B to submission of planning application (RIBA
stage 3) and associated site surveys.

    
II.         
Progression of the Weydown Road Community Hub project to submission of
a Planning Application.

  
III.         
Delegated authority to the Strategic Director -
Place to submit the required planning applications for this project
on behalf of the Council.

 
IV.         
Delegated authority to the Strategic Director -
Place in consultation with the Strategic
Director, Legal & Democratic Services to
implement the procurement strategy, and award the consultancy
services contracts.

   
V.         
Delegated authority to the Strategic Director -
Place in consultation with Strategic Director, Legal &
Democratic Servicesand Portfolio Holder for
Finance and Assets to approve and implement a procurement strategy
for the construction contracts associated with this
project.
 

Supporting Documents

Report - Weydown Road Development Business Case.pdf
Item 11 - Revised Recommendations.pdf

Details

OutcomeRecommendations Approved
Decision date9 Apr 2024
Subject to call-inYes