Sutton Gateway Phase 1
May 12, 2026 Chief Executive (Officer) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Executive Director of Transport for West Midlands approved a variation agreement for Sutton Gateway Phase 1 on 23/04/2026. An additional grant of £910,000 was awarded to Birmingham City Council, revising the total budget to £1,660,000. Key milestone dates were extended to March 2027 for the Outline Business Case and March 2032 for project delivery completion.
Details
| Outcome | For Determination |
| Decision date | 12 May 2026 |
| Effective from | 1 May 2026 |
| Lead officer | Philip Havenhand, Mo Younis |