A45 Coventry Road Cycle Route Phase 2

September 21, 2026 Investment Board (Committee) Key decision Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The West Midlands Combined Authority Investment Board noted the principles for allocating £405m of funding and engagement with local authority officers. The Board also noted progress on appointing an independent panel for scheme prioritisation and business case approvals.

Full council record

Purpose

This report is seeking £12.8m from CRSTS funding to deliver the schsme.

Decision

Resolved that:

  1. A funding allocation of £12.8m from the City Regions Sustainable Transport Settlement (CRSTS) and the Transport for the City Regions (TCR) programmes to Birmingham City Council for delivery of the A45 Coventry Road Cycle Route Phase 2 project, as set out at Section 5 of the report be approved.
  2. Authority be delegated to the WMCA Executive Director, Transport for the West Midlands to agree suitable terms and conditions to apply the grant award as set out Section 5 of the report.
  3. A progress report be submitted to Investment Board in due course to provide oversight of the delivery of the project and the collaboration group of the two local authorities.
  4. The changes to funding allocations for the East Birmingham to Solihull Corridor (Bordesley Green) and Birmingham Snow Hill Growth schemes proposed to fund the A45 Phase 2 scheme be noted.

Related Meeting

Investment Board - Monday 21st September 2026 10.30 am on September 21, 2026

Details

ReferenceCall-ins0
OutcomeFor Determination
Decision date21 Sep 2026
Effective from7 Oct 2026
Expected date21 Sep 2026
Originally due21 Sep 2026
Lead officerPhilip Havenhand, Mo Younis