BPP Package 4 Change Request

October 23, 2026 Executive Director of Transport for West Midlands (Officer) Key decision Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Executive Director of Transport for West Midlands approved the revised delivery approach for Package 4 of the Bus Priority Programme, separating it into two phases for detailed design, Full Business Case, and construction. The decision, made on 23/10/2026, approved expenditure of £1,775,189 of CRSTS funding for Phase 1 development and submission of a Full Business Case, along with a 12-month programme extension.

Full council record

Purpose

Change Request for Package 4 of the Bus Priority Programme to inform of scope changes and the need to extend the programme and budget allocated at OBC.

Decision

The revised delivery approach to separate the project into two phases for detailed design, Full Business Case (FBC) and construction was approved.

The expenditure of £1,775,189 of CRSTS funding for the development and submission of a FBC for Phase 1 of the Cross City Bus Package 4 (Longbridge/Frankley to Castle Vale/Sutton Coldfield), together with a 12?month extension to the programme, was approved.

Details

ReferenceCall-ins0
OutcomeFor Determination
Decision date23 Oct 2026
Effective from31 Oct 2026
Lead officerConchita Munar
Subject to call-inYes