Witton and Aston Stations design, development, and enabling works funding

October 28, 2026 Executive Director of Transport for West Midlands (Officer) Key decision Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Executive Director of Transport for West Midlands approved the allocation of £4.992m for Witton and Aston stations design, development, and enabling works on 28/10/2026. The Outline Business Case was also approved, alongside entering into an Implementation Agreement with Network Rail. Authority was delegated to the Director of Rail TfWM to authorise expenditure and to the Programme Sponsor to negotiate the Implementation Agreement.

Full council record

Purpose

Funding request for design, development, and enabling works funding for the Witton and Aston stations project

Decision

The allocation of £4.992m Transport for City Regions (TCR) funding for the purposes of funding the enabling works and the continued design and development work in relation to the Witton and Aston stations enhancement project was approved.

Authority was delegated to the Director of Rail TfWM power to authorise the expenditure of up to £4.992m on the delivery of these enabling works and design and development work.

The Outline Business Case for the Witton and Aston stations enhancement project was approved.

West Midlands Combined Authority entering into an Implementation Agreement with Network Rail Infrastructure Limited in respect of design and development, including Engineering Stage 5, and the enabling works of the Witton and Aston stations enhancement project was approved.

Authority was delegated to the Programme Sponsor for the Witton and Aston stations enhancement project power to negotiate and agree the terms of the Implementation Agreement or a variation to the existing Development Services Agreement.

Approval was subject to conditions outlined at section 11 within the report.

Details

Reference0
OutcomeFor Determination
Decision date28 Oct 2026
Effective from5 Nov 2026
Lead officerTom Painter, James Callingham, Jacob Barlow
Subject to call-inYes