September 16, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve Option 2 for the Olding Road project, including the refurbishment of the depot and part of the warehouse, demolition of the remaining warehouse, a solar installation, and a revised budget of £7.0 million, with officers proceeding in line with the Council’s agreed Scheme of Delegation and the Section 151 Officer making necessary changes to prudential indicators.
Full council record
Purpose
The Cabinet will be provided with an update on
the business case and delivery of the Olding Road project.
Decision
Resolved:
That:
1.
The recommended Option 2 and approach for the former depot and
warehouse, as set out in the revised business case included as
Appendix A to Report number CAB/WS/25/039, be approved.
2.
The revision of the current £7.0 million project budget
expenditure be approved, as follows:
-
£6.0 million to deliver Option 2.
-
£0.77 million budget for solar installation as a top up to
the net zero fund as detailed in Appendix D and
-
The balance (£0.23 million) to go back into the Investing in
our Growth Agenda fund uncommitted balance.
-
Of this budget, £5.77 million to be assumed to be funded
through prudential borrowing.
3.
The Portfolio Holder for Resources and the Portfolio Holder for
Leisure be supported to progress plans for the repurposing of the
remainder of the site.
4.
The enabling works of up to £1.5 million from the budget to
mitigate further programme delay, as set out in Appendix A to
Report number CAB/WS/25/039, be agreed.
5.
It be acknowledged that in line with recommendations 1., 2., 3. and
4. above, Officers to proceed in line with the Council’s
agreed Scheme of Delegation.
6.
The Council’s Section 151 Officer to make the necessary
changes to the Council’s prudential indicators, as a result
of recommendations 1., 2., 3. and 4. above.
Related Meeting
Cabinet - Tuesday 16 September 2025 6.00 pm on September 16, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Sep 2025 |
| Subject to call-in | Yes |