Leeds Inner Ring Road Structural Resilience Futureproofing

June 25, 2026 Combined Authority Board (Committee) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Combined Authority Board decided on 25/06/2026 to approve the Leeds Inner Ring Road Retaining Walls scheme proceeding to full business case and commencing delivery. The Board approved £25,355,000 of Combined Authority funding and a funding agreement with Leeds City Council, with release of £50,000 for monitoring and evaluation delegated to the Chief Executive in consultation with the Mayor. Future approvals will follow the outlined assurance pathway, approval route, and tolerances.

Full council record

Purpose

Approval for the Leeds Inner Ring Road Structural Resilience Futureproofing scheme to proceed through decision point 4 (full business case). This scheme aims to deliver maintenance works of retaining walls on Leeds Inner Ring Road.

Decision

RESOLVED:– That the Combined Authority Board, subject to conditions:

  1. Approved that the Leeds Inner Ring Road Retaining Walls scheme proceeded through decision point 4 (full business case) and work commenced on activity 5 (delivery).
  2. Approved the Combined Authority’s funding of £25,355,000. The total scheme cost was £25,355,000.
  3. Approved that the Combined Authority entered into a funding agreement with Leeds City Council for funding of up to £25,355,000, including a ring-fenced amount of £50,000 for monitoring and evaluation, release of which was delegated to the Combined Authority’s Chief Executive in consultation with the Mayor.
  4. Approved that future approvals were made in accordance with the assurance pathway, approval route and tolerances outlined in the report, subject to the scheme remaining within those tolerances.
  5. Noted that the total scheme cost included £6,085,000 (24%) for risk and contingency and £1,450,000 (5.7%) for inflation.

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date25 Jun 2026
Effective from7 Jul 2026
Expected date25 Jun 2026
Originally due25 Jun 2020
Lead officerCaroline Farnham-Crossland
Subject to call-inYes