Supply Chain Programme
July 16, 2026 Investment Board (Committee) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Combined Authority Board approved additional funding of £15,572,950 for the Highways Asset Management Programme on 25/06/2026. This increased the total programme cost to £300,644,892. The Board also approved funding agreements with partner councils for the additional allocations.
The Assistant Director Legal, Governance, & Compliance approved a constitutional amendment regarding Members' Allowance Scheme and access to the Local Government Pension Scheme on 08/05/26. This amendment reflects current statutory positions enabling elected members to rejoin the LGPS. A new section was inserted into the Members Allowance Scheme at Paragraph 13.
The Combined Authority Board approved the establishment of a West Yorkshire Housing Investment Fund programme with potential funding of up to £334,620,000 from the Integrated Settlement on 25/06/2026. They also approved development funding of up to £10,000,000 for capital programme activities and business case development. Delegations were approved for the Chief Executive, in consultation with the Mayor, to approve subsequent capital project business cases up to £20 million and to sign funding agreements. Approval was also given for the Housing Enabler Fund revenue scheme with £5,500,000 funding.
The Combined Authority Board noted updates on the English Devolution and Community Empowerment Act 2026 and the West Yorkshire Integrated Settlement on 25/06/2026. They noted the Act's provisions for Strategic Authorities and the transition into delivery from April 2026.
The Governance & Audit Committee noted the update on the 2025/26 Statement of Accounts production and the actions taken as part of the improvement plan on 02/07/2026. The Authority expects to publish its draft statement of accounts by the 30 June deadline.
Full council record
Purpose
Approval for the scheme to proceed through decision points 2 to 4 (business justification case). This scheme aims to provide a package of support to strengthen the resilience, productivity, and competitiveness of small and medium enterprise across West Yorkshire in priority sectors, including advanced manufacturing, engineering, clean energy, medical devices and construction.
Decision
West Yorkshire Supply Chain Programme
RESOLVED: – That the Investment Board, subject to conditions, and with reference to 4.50 of the report:
- Approved that the West Yorkshire Supply Chain Programme proceeds through Decision Point 2 to 4 (Business Justification) and that work commences on Activity 5 (Delivery).
- Approved Combined Authority funding of £2,000,000 for the West Yorkshire Supply Chain Programme, with a total scheme cost of £2,375,000.
- Approved that future approvals for the West Yorkshire Supply Chain Programme are made in accordance with the assurance pathway, approval route and tolerances set out in the Business Case Summary attached to the report.
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved |
| Decision date | 16 Jul 2026 |
| Effective from | 7 Jul 2026 |
| Lead officer | Joanna Kilburn |