Construction Skills Capital

July 16, 2026 Investment Board (Committee) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Investment Board approved the Construction Skills Capital scheme to proceed through Decision Point 2 to 4 and commence work on Activity 5 on 16/07/2026. The Board approved Combined Authority funding of up to £6,730,042 for the scheme. Future approvals will follow the assurance pathway and tolerances outlined in the Business Case Summary.

Full council record

Purpose

Approval for the Construction Skills Capital scheme to proceed through decision points 2 to 4 (business justification case). This scheme aims to expand teaching capacity, align the Further Education estate with high-growth sectors and address skills gaps across West Yorkshire.

Decision

Construction Skills Capital

RESOLVED: – That the Investment Board, subject to conditions, in reference to 4.30 and 4.31 of the report:

  1. Approved that the Construction Skills Capital scheme proceeds through Decision Point 2 to 4 (Business Justification Case) and that work commences on Activity 5 (Delivery).
  1. Approved Combined Authority funding of up to £6,730,042, with the total scheme cost being £6,730,042.
  1. Approved that future approvals for the Construction Skills Capital scheme are made in accordance with the assurance pathway and tolerances set out in the Business Case Summary attached to the report.

Details

OutcomeRecommendations Approved
Decision date16 Jul 2026
Expected date16 Jul 2026
Originally due25 Jun 2026
Lead officerMichelle Burton