The Combined Authority Board decided to approve the Regeneration Commercial Investment Fund programme progressing to Decision Point 2 and to commence work on individual project business cases for schemes on the RCIF pipeline. The Board also approved development funding of up to £6,000,000 for programme activities and business case development. Additionally, the Board approved a change request to the Employment Land Accelerator Fund scheme to increase delivery timescales to March 2029 and funding by £4,000,000, and approved the conversion of £4,000,000 of capital funding to revenue funding for this scheme. The Board approved a delegation to the Combined Authority’s Chief Executive, in consultation with the Mayor, to sign Funding Agreements under the Regeneration Commercial Investment Fund.
Full council record
Decision
RESOLVED:– That the Combined Authority Board:
- Approved that the Regeneration Commercial Investment Fund programme progress through Decision Point 2 (Programme Business Case) and noted the Combined Authority’s potential funding of up to £121,000,000 from the Integrated Settlement, subject to endorsement of a pipeline of projects by either the Investment Board or the Combined Authority Board.
- Approved that work commence on the individual project business cases for schemes on the Regeneration Commercial Investment Fund (RCIF) pipeline.
- Approved development funding of up to £6,000,000 for programme activities, resourcing and any business case development requirements, taking the total approval to £6,000,000.
- Approved a delegation to the Combined Authority’s Chief Executive, in consultation with the Mayor, to sign any Funding Agreements under the Regeneration Commercial Investment Fund required between the Combined Authority and partners as a consequence of approvals to subsequent capital project business cases.
- Approved the change request to the Employment Land Accelerator Fund scheme to:
· increase delivery timescales from September 2026 to March 2029; and
· increase funding by £4,000,000, taking the total from £2,000,000 to £6,000,000.
- Approved the conversion of £4,000,000 of capital funding from the Integrated Settlement (Local Growth Fund) to revenue funding for the Employment Land Accelerator Fund.
Related Meeting
Combined Authority Board - Thursday, 29th October, 2026 11.00 am on October 29, 2026
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved |
| Decision date | 29 Oct 2026 |
| Effective from | 3 Nov 2026 |
| Subject to call-in | Yes |