Installation of 2 temporary double classrooms including toilets at Foxfield School
September 26, 2025 Assistant Director: Property and Investment (Officer) Approved View on council websiteFull council record
Decision
The Assistant Director of Property and
Investment has approved that Wernick Hire Ltd (Company Number
00633778) be directly awarded a contract to the value of
£282,638.56 via the Fusion 21 Framework for Refurbishment,
Construction, New Build and Modular Building Framework – Lot
3 to undertake installation of 2 temporary modular buildings with 2
classrooms and toilets at Foxfield School, New Hey Road, Woodchurch
CH49 5LE
Reasons for the decision
A detailed Specification of requirements has
been received from Foxfield School, New Hey Road, Woodchurch, to
accommodate the increased pupil numbers for the 20225/26 school
year.
A more permanent solution of an extension to the original school is
in the planning stage but, would not be completed before the start
of the new academic year.
In this instance a direct award to Wrenick Hire Ltd via the Fusion
21 Framework for Refurbishment, Construction, New Build and Modular
Building Framework – Lot 3 was awarded to Wernick Hire Ltd
and will be underpinned by a formal contract which will be drawn up
by the Council’s legal team in due course.
Alternative options considered
A number of design options have been explored
to create the additional pupil accommodation required by the
school.
An extension to the existing building is in planning stage but
would not be completed for the 2025/26 academic year. The school
could not accommodate the increase in pupil numbers within the
existing building until the new extension was built. The option of
not proceeding with the temporary classroom project would mean that
teaching accommodation would not meet Department for Education
guidelines.
Details
| Outcome | Recommendations Approved |
| Decision date | 26 Sep 2025 |