Bus Service Improvement Plan - Delivery Plan
March 27, 2025 Executive (Other) Key decision Approved View on council websiteFull council record
Purpose
To approve the Bus Service Improvement Plan,
Delivery Plan for 25/26
Content
RESOLVED
that the Executive:
1)
agreed to the delivery of the schemes and measures
identified in Option 2 in the report.
2)
agreed to the spending of Bus Grant funding, to
allow the delivery of the schemes and measures identified in Option
2 of the report.
3)
agreed to the release and spending of £573,716
of S106 contributions, as detailed in Annex C, Part 2 of the
report, to support any decisions made in recommendations 1 and
2.
Related Meeting
Executive - Thursday, 27th March, 2025 7.00 pm on March 27, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 27 Mar 2025 |