Capital Budget Outturn 2024-2025 including Quarter One Capital Budget Monitoring 2025-2026
July 16, 2025 Council (Other) Key decision Approved View on council websiteFull council record
Purpose
To approve capital budget outturn 2024-2025
including quarter one capital monitoring 2025-2026.
Content
1.
That the revised medium term General Fund capital programme of
£404.3 million, an increase of £48.7 million from the
previously approved programme, and the change in associated
resources be approved.
2.
That the revised medium term Housing Revenue Account (HRA) capital
programme of £608.9 million, an increase of £3.1
million from the previously approved programme, and the change in
associated resources be approved.
Related Meeting
Council - Wednesday, 16th July, 2025 5.45 pm on July 16, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Jul 2025 |