To agree to a sewer easement to allow the 3 self-build homes on former HRA land to connect into a foul sewer

November 3, 2026 Director of City Development (Officer) Unknown View on council website
Full council record

Decision

Background / Decision Summary:
1. An Executive decision of 22nd October 2020 approved the disposal of eight small sites for self-build housing, including the Chaloners Road plots, and delegated authority to progress those disposals.
2. The Council disposed of the Chaloner’s Road self-build plots as part of its self and custom housebuilding programme with the third and final plot sale completing in March 2026. The three self-build plots now require a permanent connection to the public foul sewer network in order to facilitate residential development and occupation.
3. The only financially viable route for the self-builders is to make the foul drainage connection via an existing sewer located to the rear of Nos. 4-10 Chaloner’s Road. This sewer is currently a City of York Council asset. In order to allow the self-build plots to connect to the sewer, a formal sewer easement is required across Council-owned land.
4. Yorkshire Water has confirmed that, following completion of the necessary legal arrangements and adoption process undertaken by the 3 self-build applicants, the entire sewer will be adopted as part of the public sewerage network, including the sewer that serves the six council owned flats, reducing the financial burden of ongoing maintenance to the council. In the meantime, in lieu of formal adoption, the self-build applicants take proportionate responsibility / liability for the repair and maintenance of the asset. The granting of the easement is necessary to enable the drainage infrastructure serving the self-build plots to be completed and subsequently transferred into Yorkshire Water ownership and maintenance responsibility.
5. The self-build plot owners have requested that the Council enter into the required sewer easement and have agreed to meet all reasonable legal and associated professional costs incurred by the Council in preparing, negotiating and completing the easement documentation.

Implications:
Financial: As the self-builders have agreed to meet all reasonable legal and associated professional costs incurred by the Council there are no financial implications.

Legal: The council’s Legal Services Department have been consulted to ensure that the draft easement mitigates all risk to the council.

Property: This will enable the council to get a current CYC drainage asset to be adopted by Yorkshire Water with all responsibility for maintaining it transferring to Yorkshire Water.

Comments/Observations:
This decision will support the development of self-build housing on a vacant site.