To proceed with the agreed heads of terms, and once the conveyancing is complete, to dispose of the former Tang Hall library site to a developer to deliver up to 9 self-contained 1 and 2-bedroom supported living apartments which have been co-designed

October 29, 2026 Director of City Development (Officer) Unknown View on council website
Full council record

Decision

Background / Decision Summary:
1. Since 2020, the council have been working with a group of parents whose young adults have learning disabilities. These parents have come together to form the ‘CosyHome’ project whose objective is to create a housing development where the young adults can move out of the family home and live as independently as possible with support. The group have worked with the council’s Community and Self Build Officer to find a suitable plot of land on which to develop this cohousing, as well as working with individuals from Integrated Commissioning and Adult Social Care.
2. In October 2021, the Council Executive noted the progress made on bringing forward a proposal for a Community Led Housing project on the former Tang Hall Library site, and approval was given to dispose of the site on a long lease to enable the delivery of community housing.
3. The community group are now working with a developer, and an RP, to build a new supported living development to house young adults from the community group. To ensure the development is viable there will also be additional apartments which the council can have nominations rights for.
4. The developer has made an offer for the land that meets the RICS certified valuation and the Heads of Terms (HOT’s) for the sale have been developed, subject to final sign off by the council.
5. The creation of this bespoke cohousing community that seeks to meet the specific needs of the CosyHome young adults. The project has been developed over a number of years by families seeking a sustainable, long-term housing solution as parents / carers grow older and less able to care for their loved ones, designed to promote independence, wellbeing and support for young adults.
6. In addition to seeking to meet the needs of members of the cohousing group, the development will also deliver a small number of additional homes for other individuals in housing need, increasing the supply of specialist supported accommodation within the local authority area, mitigating the likelihood that those in need of supported housing would need to move outside of the York area.
7. The proposal supports the Council's objectives to increase the provision of specialist housing, promoting independent living in individual flats (rather than shared housing), and seeks to deliver positive social outcomes for residents.
8. The Heads of Terms have been structured in such a way to enable the development to go ahead while still allowing the land to be sold at market value. This means a guaranteed capital receipt for the council’s general fund with the disposal being a long leasehold sale. There is a long stop date in the contract for the completion of the development to ensure the site cannot be land banked.

Implications:
Financial: This land is being sold at a value in line with a certified RICS valuation and will bring in a capital receipt for the council.

Legal: The councils Legal Services Department (LSD) have been consulted to ensure that all aspects of the land sale comply with the councils constitution. The heads of terms for the sale have been drafted in consultation with the councils LSD.

Property: the site is currently vacant and hoarded off. While there are no current issues with the site, if it were to continue to sit empty there is the real possibility of the site attracting anti-social behavior which would cost the council officer time and money to deal with.

Comments/Observations:
This decision will support the development of supported housing on a vacant site.
Decision:
To proceed with the agreed heads of terms to sell the former Tang Hall library site to the specified developer.

Supporting Documents

Former Tang Hall Library Site - Heads of Terms 2025 - v9.docx.pdf

Details

OutcomeDecision Made
Decision date29 Oct 2026