Decision

FP2094 VARIATION TO HOUSING MAINTENANCE CONTRACT

Decision Maker:

Outcome: Recommendations Approved

Is Key Decision?: No

Is Callable In?: Yes

Date of Decision: January 7, 2025

Purpose:

Content: Decision taken Cabinet agreed the variation to the Equans contract which would change the way payments were made.   Reason for decision In February 2023, Cabinet agreed to award a contract to Equans for planned housing works. The scope of the contract includes replacement kitchens, bathrooms, windows and roofs.   An opportunity had arisen to change contract prices in relation to the preliminaries and scaffolding costs which result in a significant saving. Full details were included in the Part 2 report.

Supporting Documents

corporate report template part i - equans variation.pdf

Related Meeting

Cabinet - Tuesday 7th January 2025 6.30 pm on January 7, 2025