Decision

Autism Spectrum Condition (ASC) Units Capital Project

Decision Maker: Delegated Decisions

Outcome: Recommendations Approved

Is Key Decision?: No

Is Callable In?: No

Date of Decision: March 25, 2025

Purpose: To consider approving the additional resource and spend approval for the capital project to create two new ASC units at Bradwell Village and Priory Common Schools.

Content: That the additional resource allocation and spend approval in the 2025/26 Capital Programme of £400k, funded from the Special Provision Fund (Grant funding from Central Government), to allow the capital works at both schools to progress to create ASC Units for SEND pupils, be approved.

Supporting Documents

Autism Spectrum Condition ASC Units Capital Project.pdf

Related Meeting

Delegated Decisions - Tuesday 25th March, 2025 6.00 pm on March 25, 2025