Decision

Park Row, Perry Road, Upper Maudlin Street and Colston Street

Decision Maker: Executive Director: Growth and Regeneration

Outcome: Recommendations Approved

Is Key Decision?: No

Is Callable In?: No

Date of Decision: June 16, 2025

Purpose: An Officer Decision Notice authorising the commissioning the contractor for works to Park Row, Perry Road, Upper Maudlin Street and Colston Street was published on 27 November 2023. This Officer Decision Notice reflects the final contract value, following construction.

Content: The Executive Director for Growth and Regeneration (in consultation with the Chair of the Transport and Connectivity Committee, the S151 officer, and the Head of Legal Services) has authorised the change to the contract value. The original contract value: £2,224,990.19, final contract value: £2,649,547.37 (an increase of £424,557.18).