Decision

Decision to approve an Early Works Instruction in respect of Peterchurch Primary School project for early procurement and site mobilisation works

Decision Maker: Service Director - Education, Skills and Learning

Outcome: Recommendations Approved

Is Key Decision?: No

Is Callable In?: No

Date of Decision: June 16, 2025

Purpose:

Content: Decision to approve an Early Works Instruction under the Pre-Services Construction Agreement in respect of the Peterchurch Primary School project for enabling works to be instructed. The Early Works Instruction 2 will instruct early procurement and site mobilisation works at a cost of £168,083.27 due to a long lead in time and to ensure there is not a delay to programme, this is within the budgets set aside for these elements of the project.

Supporting Documents

Peterchurch - RoOD for EWI 2 - June 2025 v2.pdf