Decision

FP2168 Approval of appropriation of land

Decision Maker: Cabinet

Outcome: For Determination

Is Key Decision?: No

Is Callable In?: Yes

Date of Decision: September 2, 2025

Purpose:

Content: Decision taken   The Cabinet:   a)    approved progression of the scheme and endorsed the procurement approach. b)    approved the appropriation of the land from the General Fund to the Housing Revenue Account at £4 million in line with the external valuations previously conducted at the time the agreement was signed. c)    approved that the procurement exercise commences for a contractor to develop the site, utilising the Pretium Framework. d)    noted the requirement for allocation of further funding to be completed as part of the standard budget setting process.  

Supporting Documents

YMCA Peartree Lane Draft Report Part I 2025.pdf

Related Meeting

Cabinet - Tuesday 2nd September 2025 6.30 pm on September 2, 2025