Capital Budget Monitoring – Quarter 1, 2025/26
Decision Maker: The Executive
Outcome: Recommendations Approved
Is Key Decision?: No
Is Callable In?: No
Date of Decision: September 23, 2025
Purpose:
Content: It was resolved – · To note the progress of expenditure and receipts against the capital budget 2025/26 at Quarter 1. · To approve the additional schemes, amounting to £9.363m to the capital programme and amendments to funding as per Appendix C to the report, which will result in a revised capital budget of £56.186m for 2025/26.