Decision

Selsey Coastal Scheme - Proposed Accelerated Works

Decision Maker: Cabinet

Outcome: Recommendations Approved (subject to call-in)

Is Key Decision?: No

Is Callable In?: Yes

Date of Decision: December 2, 2025

Purpose: 1.1 This report seeks approval to submit an application to the Environment Agency for Grant in Aid (GiA) funding to deliver accelerated coastal defence works at West Beach, where existing defences are deteriorating. The proposed works aim to reduce the risk of defence failure in advance of the Selsey Coastal Scheme.

Content: RESOLVED   That Cabinet:   1.    Approves the submission of an application to the Environment Agency for Grant in Aid funding to deliver accelerated works to the West Beach frontage, via a Business Case Update Report. 2.    Approves the procurement and appointment of a contractor and subsequent construction of the accelerated works, subject to the securing of full Grant in Aid funding (paras. 4.3 and 4.4). 3.    Approves that delegated authority be granted to the Director of Planning and Environment, in consultation with the Chief Operating Officer and Director of Corporate Services: to appoint contractors to agree project financial tolerances and to authorise expenditure of the Grant in Aid funding. 4.    Notes the current funding uncertainties at this stage (Para. 4.4 and 7.3).  

Supporting Documents

Selsey Coastal Scheme - Proposed Accelerated Works - Report.pdf
Selsey Coastal Scheme - Proposed Accelerated Works - Appendix A.pdf
Selsey Coastal Scheme - Proposed Accelerated Works - Appendix B.pdf

Related Meeting

Cabinet - Tuesday 2 December 2025 9.30 am on December 2, 2025