Decision
North Hykeham Relief Road (NHRR) - Proceed to Construction
Decision Maker: Executive
Outcome: Recommendations Approved
Is Key Decision?: Yes
Is Callable In?: No
Date of Decision: January 6, 2026
Purpose: As detailed in the report.
Content: 1. That the issuance of the contractual instruction to Balfour Beatty under the terms of the existing two-stage contract to proceed with the construction of the NHRR, subject to confirmation by the Department for Transport that the Full Business Case is approved, be approved; and 2. That authority be delegated to the Executive Director of Place, in consultation with the Executive Councillor for Highways and Transport, to negotiate minor changes to the existing contract with Balfour Beatty and enter into a Deed of Variation in respect of the existing agreement.
Supporting Documents
Related Meeting
Executive - Tuesday, 6th January, 2026 10.30 am on January 6, 2026