Decision

Roof Replacements 2024/25

Decision Maker: Cabinet

Outcome: Recommendations Approved

Is Key Decision?: Yes

Is Callable In?: No

Date of Decision: September 25, 2024

Purpose: To approve commencement of a tendering process for a contractor to undertake roof replacements to various properties throughout the Borough.

Content: Cabinet:     1.     Approved the procurement of a contract with a total value of up to £4,000,000 to the end of Financial Year 25/26, for the replacement of roofs to HRA properties across the Council.   2.     Delegated approval of the award of the contract, contract terms and completion to the Strategic Director of Place, acting in consultation with the Strategic Director of Resources and the Deputy Director of Legal & Governance  

Supporting Documents

Roofing Renewals to HRA Properties 24-26 - Cabinet Report v2.docx.pdf
Appendix 1 - EqHIA - Roof Replacements.docx.pdf

Related Meeting

Cabinet - Wednesday, 25th September, 2024 7.30 pm on September 25, 2024