Subscribe to updates
You'll receive weekly summaries about Boston Council every week.
If you have any requests or comments please let us know at community@opencouncil.network. We can also provide custom updates on particular topics across councils.
Prefer no ads? Become a Supporter for £3.50/month
Audit & Governance Committee - Monday, 29 June 2026 - 6.30 pm
June 29, 2026 at 6:30 pm Audit & Governance Committee View on council websiteSummary
Open Council Network is an independent organisation. We report on Boston and are not the council. About us
The Audit & Governance Committee of Boston Council met on Monday 29 June 2026 to review the Council's risk management, assurance, financial statements, and treasury management activities for the 2025/26 financial year. Key decisions included noting the quarterly risk report, the combined assurance status report, the internal audit annual report and opinion, and the draft annual governance statement. The committee also received the unaudited financial statements and the annual treasury report for noting, with recommendations for approval to be made to the full Council.
Quarter 4 25/26 Risk Report
The committee received an update on the Council's strategic, partnership, and fraud risks as at 31 March 2026. Several key risks were discussed, including the Environment Act (High Risk), Capacity/Change Readiness and Workforce Resilience (Medium Risk), and the Local Plan (High Risk). The report noted that the highest-rated strategic risks remained those relating to budget, the Environment Act, cyber incidents, and the Local Plan. Updates were also provided on the Partnership Risk Register, with significant risks identified as Local Government Reorganisation, funding pressures, and staffing resilience. No significant changes were identified within the fraud risk register, with a review due to commence in Quarter 1 of 2026/27. The committee welcomed the comprehensive overview and noted the positive progress in reducing identified risks. Councillor Ralph Pryke declared a personal interest as a Director of Public Sector Partnership Services Ltd (PSPS) during the discussion. The committee resolved to note the quarterly risk monitoring information for Quarter 4 2025/26.
Combined Assurance Status Report 2025/26
The committee reviewed the Combined Assurance Status Report for 2025/26, which provided an overview of the Council's assurance framework and an assessment of governance, risk management, and control arrangements. The report indicated a stable and positive overall assurance position, with strong governance and partnership working. Areas requiring continued oversight included financial resilience, implementation of the Uniform system, and legacy server infrastructure. The report also detailed assurance assessments across directorates, partnerships, and major projects. Members welcomed the positive assurance position and noted the increase in green-rated activities. Discussions covered financial resilience, a Senior Information Risk Owner (SIRO) incident related to a software supplier patch failure, and a separate reportable data protection incident. The committee resolved to note the Combined Assurance Status Report 2025/26.
Internal Audit Annual Report and Opinion 2025/26
The committee received the Internal Audit Annual Report and Opinion for 2025/26, which summarised audit activity and provided the Head of Internal Audit's opinion on the adequacy and effectiveness of the Council's governance, risk management, and control framework. The Council received an overall Adequate Assurance Opinion
for 2025/26. Discussions focused on areas requiring improvement, including the identification and monitoring of savings, risk management framework strengthening, and informal training arrangements. Members also discussed the committee's ability to undertake effective real-time scrutiny and escalation arrangements for savings proposals. The committee resolved to note the Internal Audit Annual Report and Opinion 2025/26.
Unaudited Financial Statement 2025/26
The committee received the Unaudited Financial Statements for 2025/26, which provided an overview of the Council's draft Statement of Accounts prior to external audit. The accounts were completed and published ahead of the statutory deadline. Discussions covered the implementation of the Environment Act and food waste collections, Internal Drainage Board (IDB) levies, and specific disclosures within the accounts, including reductions in income and capital programme expenditure. The committee noted the positive year-end financial position and congratulated the finance team on producing the unaudited accounts within the statutory deadline. The committee resolved to note the Unaudited Financial Statements 2025/26.
Annual Treasury Report 2025/26
The committee received the Annual Treasury Report for 2025/26, which reviewed treasury management activity and confirmed compliance with the Council's Treasury Management Strategy and CIPFA Treasury Management Code. The report detailed the Council's borrowing and investment position as at 31 March 2026, including £1.01 million of fixed-rate borrowing and investments totalling £35.382 million. Discussions focused on the performance of property fund investments, the longer-term outlook for commercial property investments, and investment diversification. The committee welcomed the strong treasury returns achieved and acknowledged the contribution of treasury management to the Council's financial position. The committee resolved to recommend to Full Council the approval of the Annual Treasury Report 2025/26.
Draft Annual Governance Statement (AGS) 2025/26
The committee reviewed the Draft Annual Governance Statement for 2025/26, which assessed the effectiveness of the Council's governance arrangements. The statement identified areas for further improvement, including financial resilience, risk management, implementation of audit recommendations, Local Government Reorganisation, and the budget-setting process. Discussions noted that several governance actions reflected issues previously considered by the committee. The committee resolved to note the Draft Annual Governance Statement (AGS) 2025/26.
Work Programme
The committee received the Work Programme for the 2026/27 municipal year. Members suggested the inclusion of further information on the Council's approach to artificial intelligence governance and oversight. The committee welcomed the opportunity to influence its future work programme and supported the inclusion of emerging governance issues. The committee resolved to note the Work Programme.