Climate Emergency Overview and Scrutiny Committee - Tuesday, 15 September 2026 - 7.00 pm
September 15, 2026 at 7:00 pm Climate Emergency Overview and Scrutiny Committee View on council websiteSummary
Open Council Network is an independent organisation. We report on Wokingham and are not the council. About us
The Climate Emergency Overview and Scrutiny Committee met to review progress on the Climate Emergency Action Plan (CEAP), focusing on transport and renewable energy projects. The committee noted the progress made in delivering transport-related actions and that member comments and queries would inform future work on the Transport section of the CEAP. The committee also noted the update on the current position of the solar energy projects and that further information would be provided in response to member queries. The committee confirmed its work programme for the upcoming year.
CEAP Transport Review
The committee reviewed the progress made on transport-related actions within the Climate Emergency Action Plan (CEAP) and the Local Transport Plan. Key achievements highlighted included the installation of 415 public Electric Vehicle (EV) charge points, an increase in EV mileage share to 6.3%, and active travel mileage reaching 7.2% against an 8% target. Bus mileage share stood at 11.1%, with 2.6 million bus passenger journeys recorded, and six electric buses were introduced on Route 21. Major schemes such as the Woodley to Reading active travel scheme and planned improvements at Woosehill Roundabout were also noted.
However, areas requiring further work were identified, including improving the quality and representativeness of mode share data, progressing the next phase of on-street EV charging procurement, and developing a freight strategy. Councillors raised questions regarding the effectiveness of the Council's new supplier for the ORCS chargepoint project, OpCharge, and requested more financial information on revenue and costs. The positive growth in bus journeys was attributed to a comprehensive review of the bus network and continued support through the Bus Service Improvement Plan. The committee also discussed the usage figures for Earley railway station and proposals to attract more users, noting that Twyford station's increased usage was linked to its role as an interchange for the Elizabeth Line. Concerns were raised about the Woodlands Avenue cycle lane, with a request for more data on cyclist usage, and the need for better signage at road junctions. Details on the School Streets programme were also sought, with officers confirming that work was ongoing to identify a suitable site for a pilot project. The challenges in measuring modal shift due to a lack of local data were acknowledged, with a comprehensive monitoring and evaluation programme developed for the Woodley to Reading active travel scheme. The impact of extreme summer weather on walking and cycling levels was also noted as a factor for future consideration. The programme for developing the freight strategy was discussed, with officers confirming that a study of freight traffic in the Borough would be completed to review CEAP targets. Members also requested more details on the costs of different types of EV charging.
The committee resolved to note the progress made in delivering transport-related actions and that member comments and queries would inform future work on the Transport section of the CEAP.
Renewable Energy Projects Update
An update was provided on the Council's three principal renewable energy projects within the CEAP: Barkham Solar Farm, Mereoak Solar Canopies, and Solar Farm 2. Barkham Solar Farm is progressing towards delivery, with detailed design work completed and a non-firm grid connection and energisation programme anticipated in Autumn 2027. The final contract price was reported to be lower than previously indicated, with an annual income projection remaining above £1 million. The Mereoak Solar Canopies project is also advancing through procurement and detailed design, with completion expected by summer 2027. This project will deliver a 1.36MW solar canopy, battery storage, and a substantial EV charging hub.
Solar Farm 2 remains paused due to its allocation of Gate 1 status under the National Energy System Operator's (NESO) connection reforms, and its status will be monitored and reviewed in response to future changes in the connection regime. During the discussion, clarification was sought on the timeframe for signing the contract with Equans for Barkham Solar Farm, with confirmation that it was expected within days. Concerns were raised about the level of curtailment projections for Barkham Solar Farm, given its initial operation under a non-firm grid connection. Officers confirmed that the business case indicated low levels of curtailment based on technical assessments. The committee also sought clarification on whether a separate business case existed for battery storage at Mereoak, which officers confirmed had been submitted to the Executive in May 2026. A request was made for exact figures on the energy to be generated by the solar canopies, and officers undertook to provide further details. The impact of increasingly hot summers on the effectiveness of solar energy projects and their income generation was also raised, with officers agreeing to provide a written briefing.
The committee resolved to note the update on the current position of the solar energy projects and that further information would be provided in response to member queries.
Work Programme
The committee reviewed its work programme for 2026-27. It was noted that Professor Chris Merchant from the University of Reading would attend the November meeting as a guest speaker, and representatives from the Royal Berkshire Fire & Rescue Service would attend the January 2027 meeting.
The committee resolved to confirm the Committee's 2026-27 work programme, as amended.
Action Tracker
The committee considered the regular Action Tracker report and resolved to note the Action Tracker report.