Long Eaton Town Deal Board - Friday, 20th November, 2026 9.30 am
November 20, 2026 at 9:30 am Long Eaton Town Deal Board View on council websiteSummary
Open Council Network is an independent organisation. We report on Erewash and are not the council. About us
The Long Eaton Town Deal Board was scheduled to consider progress on programme milestones, receive project updates, and endorse a monitoring and evaluation report. A verbal update on the Communications Plan was also on the agenda.
Long Eaton Town Deal Programme Milestones
The Board was scheduled to consider the progress against programme milestones for various projects within the Long Eaton Town Deal. According to the Long Eaton Town Deal - Programme Milestones Report
, several projects were either complete or on schedule. The Britannia Mills Bridge had been completed in June 2026, and the Broad Street Bridge & Waterfront was scheduled for completion in September 2026. The High Street and Galaxy Row projects were both on schedule for completion in March 2027 and April 2027, respectively. The Stable Block was completed in January 2026.
Project Updates
An update on project activities since the last meeting was scheduled to be presented. The Long Eaton Town Deal - Project Update Report
detailed the status of several key projects. For the Stable Block, all studios were reported to be under occupation, with 11 businesses across 14 units, nine of which had already moved in. The Long Eaton High Street project, involving repaving and public realm works, was progressing well, with significant areas of paving completed. The Galaxy Row redevelopment had entered its superstructure phase, with brickwork visible above hoarding. The West Park Waterfront and Broad Street Bridge projects were noted as complete, with only snagging items and drainage connections remaining. The West Park Events Field and West Park Lighting projects were also confirmed as complete.
Monitoring and Evaluation Report
The Board was scheduled to consider endorsing the Local Regeneration Fund Report for the period of 1 April 2026 to 30 September 2026. This report, which subsumes the Long Eaton Town Deal funding, details the overall progress of the programme. The report indicated that all five Long Eaton Town Deal projects were either complete or in delivery, with substantial construction expected to be completed by spring 2027. The report also highlighted that costs had escalated due to factors like Brexit and the pandemic, leading to the cancellation of two initial projects and the reallocation of funds. Value engineering had been employed to manage cost increases on other projects. Risks identified included potential contractor administration, flood risk, unforeseen compensation events, and the scale of benefits unlocked being less than expected.
Communications Plan Update
A verbal report on the Communications Plan was scheduled to be provided. Earlier communications focused on road closures in Long Eaton town centre and media coverage of the Britannia Mills Bridge opening. Future communications were planned to focus on the upcoming Broad Street Bridge opening event.
Date of Next Meeting
Members were asked to note that the next meeting was scheduled to take place on 26 February 2027, at 9:30 am at Long Eaton Town Hall.