Subscribe to updates
You'll receive weekly summaries about Kingston upon Hull Council every week.
If you have any requests or comments please let us know at community@opencouncil.network. We can also provide custom updates on particular topics across councils.
Prefer no ads? Become a Supporter for £3.50/month
Overview and Scrutiny Management Committee - Friday, 20 November 2026
November 20, 2026 at 10:00 am View on council websiteSummary
Open Council Network is an independent organisation. We report on Kingston upon Hull and are not the council. About us
The Overview and Scrutiny Management Committee of Kingston upon Hull Council was scheduled to consider a range of financial and regeneration matters. Key discussions were expected to focus on the Medium Term Financial Plan, capital funding for the East Bank Urban Village, and the potential use of a Compulsory Purchase Order for Pier Court.
Medium Term Financial Plan Update
The committee was scheduled to receive an update on the Medium Term Financial Plan (MTFP) projections for the period 2027/28 to 2029/30. The report indicated a sustained deterioration in the financial position, with projected deficits in future years, despite a three-year funding settlement for local government. The report highlighted that high levels of inflation were likely to outweigh the increase in funding. It also noted government policy announcements from the Autumn Budget Statement, such as an increase in the threshold for Small Business Rate Relief and energy relief for households, but stated that no specific funding allocations for local government were announced. The report was expected to outline a financial strategy to inform future budget proposals and noted that the council faced significant uncertainty, with a potential deficit of approximately £12 million in 2027/28 based on current assumptions. The report also detailed financial sensitivities related to inflation, demand pressures in social care, and the impact of efficiency savings.
East Bank Urban Village Capital Funding
A report was scheduled to seek capital funding commitment and authorisations for the delivery of the East Bank Urban Village Phases 0, 1, and 2. This large-scale, residential-led allocation in Hull's adopted Local Plan has a development agreement with ECF (English Cities Fund)1. The report was expected to request a Council commitment of £17 million towards the project, to address viability gaps and cover Council project staffing and consultancy fees. This funding was to be allocated across the phases: £1 million for Phase 0 (remediation and enabling works), £3.5 million for Phase 1 (115 affordable homes), £11 million for Phase 2 (approximately 267 affordable and Build to Rent apartments), and £1.5 million for Council project staffing and consultancy fees over five years. The funding commitment was conditional on proportional grant funding from other funders, including Homes England and Hull & East Yorkshire Combined Authority (HEYCA).
Compulsory Purchase Order for Pier Court
The committee was scheduled to consider a report seeking delegated authority to use a Compulsory Purchase Order (CPO) for Pier Court, 64 Queen Street, Hull, HU1 1XA, if it could not be acquired by agreement. This property is located within the Fruit Market regeneration area, and the report detailed efforts to acquire it by negotiated agreement with the owner, Queensway Properties Limited. The report highlighted that two planning approvals were in place for Pier Court, one from the owner for a single-storey extension to create 30 flats, and a more comprehensive redevelopment by Wykeland Beal for 33 residential units and retail space. Wykeland Beal, acting on behalf of the Fruit Market LLP, had made considerable efforts to negotiate a sale since 2021, but the owner had rejected offers. The report argued that the use of CPO powers was necessary to facilitate the continued development of the Fruit Market regeneration area and to secure a sustainable and achievable regeneration of this prominent site.
2026/27 Capital Monitoring
An updated Capital Programme for 2026/27 to 2028/29 was scheduled for review, along with an overview against budget and planned activity. The report was expected to seek authorisation for amendments to the programme, including additional funding of £0.917 million through the reallocation of programme contingencies to finalise the Hull Maritime – Queens Gardens project. The report detailed capital spend up to the end of September 2026 and outlined revisions to the programme based on updated profiling forecasts, external grant funding, and new schemes.
Treasury Management Strategy Review
A mid-year review of the Treasury Management Strategy Statement and Annual Investment Strategy for 2026/27 was scheduled. The report was to provide an update on treasury management activity and performance in the first half of the financial year, as required by the council's Treasury Management Policy Statement. It was expected to cover economic updates, reviews of the strategies, the council's capital expenditure and financing, investment portfolio performance, borrowing strategies, and compliance with treasury and prudential limits. The report noted that treasury management officers had operated within the approved strategy, safeguarding investments while ensuring liquidity and return.
Extension of Public Health Nursing Service Contracts
The committee was scheduled to consider a report seeking approval to extend existing contracts for the 0-19 Integrated Public Health Nursing Service and the Unintentional Injuries and Safer Sleep Service for a period of 12 months. This extension was to be implemented through a Deed of Variation, pending a formal process for longer-term commissioning. The report sought approval to delegate authority to the Director of Public Health for this extension. The purpose of the extension was to ensure continuity of these statutory and preventative services while further work was undertaken to review value for money, strategic priorities, and commissioning options.
Other Scheduled Items
The committee was also scheduled to receive an update from the Executive Director of Corporate Resources, consider the exclusion of the press and public for exempt items, and review the Work Programme and Outstanding Actions.
-
ECF (English Cities Fund) is a joint venture between Muse Developments, Homes England, and Legal & General, focused on regenerating urban areas. ↩