Subscribe to updates

You'll receive weekly summaries about Norfolk Council every week.

If you have any requests or comments please let us know at community@opencouncil.network. We can also provide custom updates on particular topics across councils.

Infrastructure and Development Select Committee - Thursday, 12 November 2026

November 12, 2026 at 10:00 am View on council website  Watch video of meeting Read transcript (Professional subscription required)

Chat with this meeting

Subscribe to our professional plan to ask questions about this meeting.

“Will gritting routes be reduced by 5%?”

Subscribe to chat
AI Generated

Summary

Open Council Network is an independent organisation. We report on Norfolk and are not the council. About us

Norfolk County Council's Infrastructure and Development Select Committee met on 12 November 2026 to scrutinise budget proposals for 2027-28, review new cycle lanes in Gorleston and Great Yarmouth, and consider flood risk work. No final budget decision was taken — its comments will inform a Cabinet decision in January 2027 and a Full Council decision in February 2027 — and a proposed further review of the cycle lanes was voted down. The committee also agreed changes to its future work programme.

Budget proposals for 2027-28

The committee considered, but did not decide, the savings proposals set out in the report considered by Cabinet on 5 October 2026, and recorded agreement that it had addressed the recommendations in the 261112 Infrastructure and Development Select Committee Agenda.

Officers said the proposals totalled £32.3m for 2027-28, leaving a gap of around £6m to close. The council's medium-term financial strategy1 gap over 2027-28 to 2030-31 was put at £148.5m, with a 2027-28 gap of £35.9m before the new proposals. Final decisions on council tax — Cabinet agreed to consult on increases of 3% and 5%, within the referendum threshold2 — will be made in February 2027.

Most discussion focused on infrastructure proposals in the committee's remit, including a 5% reduction in the treated gritting network, a 5% reduction in highway maintenance revenue activities, reduced verge grass cutting, reduced weed-killing, fewer hazardous waste events, and recycling centre changes.

On gritting, members raised concerns about safety, rural isolation, bus routes, school transport, emergency access and agricultural vehicles. Councillor Alexandra Kemp cited Station Road, Clenchwarton as a bus route she said was not gritted. Officers said the proposals were for consultation only, that statutory duties and risk assessments would apply, that about 2,200 miles are treated in a full gritting run so 5% would be about 110 miles, and that the aim would be to keep at least one treated route into and out of every community. They said routes are treated in seven weather domains, typically 70 to 80 times a season between October and April, often overnight, and that parish and town council grit bins — about 2,000, refilled twice a season — were not proposed for removal.

One councillor asked what criteria would be used. Officers said local circumstances, scheduled bus routes, employment, community facilities such as GP surgeries, and safety and accessibility issues at junctions would be considered, but detailed assessment would follow the consultation, which closes in early December and is due to be reported to Cabinet on 25 January 2027.

On recycling, members discussed Morningthorpe and Docking. Officers explained Morningthorpe had already closed because the landlord would not renew the lease, that the site had only three parking spaces and a limited range of materials, and that residents were being directed to larger sites including Norwich South, with a planned replacement at Spooner Row, Wymondham. The closure of Docking Recycling Centre, proposal INF003, was removed by Cabinet in October and will not be consulted on. Members also questioned fly-tipping, extra travel — put at 15 to 20 minutes to Norwich South — and capacity at neighbouring sites. Officers said booking-system data showed many Morningthorpe users already travelled to larger sites.

Members also challenged proposals to reduce hazardous waste disposal events from two a year to one, citing environmental protection. Officers said uptake had fallen — about 50% at some sites and around 90% in Norwich on the first event — that about 80% of material received was water-based paint, which can be dried with the lid off and put in residual waste, and that the aim was to reduce hazardous waste at source. One councillor said:

surely any waste, any hazardous material that is not dumped in our environment, that people get fed up of storing, surely even 70% to me is an acceptable number

Other proposals discussed included verge cutting and weed-killing, the latter reducing treatments from two a year to one for a £110,000 saving. Officers said weed-killing is mainly in urban areas on footways and kerb lines, with limited overlap with rural verge cutting, and that the changes would return services to levels seen three or four years earlier. Members asked whether cumulative effects on footway width for wheelchair users, mobility scooters and pushchairs had been assessed. Officers said safety and accessibility would be considered by area teams and that equality impact assessments3 would accompany proposals with service impacts.

Members asked about one-off savings, recurring savings and efficiencies. Officers said about £1.65m to £1.7m of the infrastructure proposals were one-off, including use of reserves which reverse the following year, and pointed to benchmarking, including work with the Future Highways Research Group, and trials such as Roadmender for pothole repairs. They said the JCB Pothole Pro was not being taken forward.

Members also noted other items, including establishment changes in the Infrastructure Delivery Team and Highways Boundary Team — officers described these as minor restructurings and fee-earning changes — building maintenance, flood risk staffing, and parking enforcement. A member raised the Highways Boundary Team's reported backlog, with a target of 12 weeks, and officers said comments would be fed back. Questions on home-to-school transport and the Fire and Rescue Service were redirected to other committees.

Middleton Road and Jellicoe Road cycle lanes

The committee noted the review requested by a Full Council motion on 28 May 2026 of the cycle and pedestrian facilities on Middleton Road, Gorleston and Jellicoe Road, Great Yarmouth.

The schemes delivered just under 2.2 miles of segregated cycle path, five formal pedestrian crossings and 18 side roads with priority for walking, wheeling and cycling. Officers said the total cost was £3.79m — £2,446,954 for Middleton Road/Church Lane and £1,344,743 for Jellicoe Road — funded entirely by ring-fenced government grant funding from Active Travel England4, with no local funding. They said any significant changes would require Department for Transport approval, could lead to reduced or withheld future funding, and that authorities which prematurely remove or weaken active travel schemes should expect less funding.

Members questioned the evidence in the report. Councillor Barry Gravenor, who declared an interest as proposer of the original motion and a resident of Middleton Road, said the report included commentary from Cycling UK but no equivalent summary from residents, traders, motorists or disability groups, and claimed no adverse traffic impact while pedestrian movements had fallen by 10%. Officers said traffic flow on Middleton Road had increased by 14% in the May to September comparison, cycle flows by 16%, bus journey times had improved by five to 10 seconds, and Jellicoe Road journey times were unchanged. They said pedestrian movements fell from 488 to 438 a day, that this did not prove the scheme caused the change, and that the Jellicoe Road monitoring camera was out of service due to water damage, with a replacement expected by the end of October 2026. They accepted there was no quantified local satisfaction measure in the report, that no post-implementation feedback had been sought from residents and businesses, and that the florist on Middleton Road — whose parking was rearranged during construction — had not been revisited since completion.

Members raised concerns about zebra crossings on roundabout exits at Middleton Road and Church Lane, pavement widths for mobility scooters and wheelchairs, delivery vehicle access and Highway Code Rule 1405 on parking in mandatory cycle lanes. Officers said stage 3 road safety audits6 had identified issues such as trip hazards and drainage, most rectified with some outstanding, that most properties have off-road driveways, and that delivery vehicles were observed using driveways, parking areas and, in some cases, the cycle lane.

Other members supported retaining the schemes, argued scrutiny should focus on future routes and promotion of use, and asked for better 12-month monitoring of car and taxi journey times, traffic displacement, accessibility and business feedback, and for work with the NHS, schools and employers. Officers said post-project reviews are standard and that a proportionate increase in monitoring of the wider network could be considered, noting monitoring itself has a revenue cost.

A recommendation by Councillor Barry Gravenor that the report did not provide sufficient evidence to address the original motion and that a further post-implementation review be undertaken was put to a vote. It was not carried, with four in favour, three against and the rest abstaining.

Flood risk management

The committee agreed to recognise and support the ongoing work of County Council teams and multi-agency partners to improve flood resilience, help communities prepare for flooding and encourage residents to take practical steps.

Councillor Kabeer Kher, Cabinet Member for Business, Skills and Agriculture, introduced the update. More than 45,000 residential properties in Norfolk are estimated to be at risk in a 1% annual probability rainfall event7, and Norfolk ranks 17th out of 153 local authority areas for surface water flood risk. Between January 2025 and August 2026 there were 61 reports of internal flooding, with two summer storms in June and July 2025 accounting for about 75%.

Progress reported included first-phase delivery of the Saham Toney flood alleviation scheme, continued development of the Dereham scheme, Natural Flood Management through Reclaim the Rain, and 988 substantive planning consultation responses in 2025 as Lead Local Flood Authority8. Officers said property flood resilience measures were installed at only 12 properties in 2025-26 due to contractor performance, with a new supplier, Watertight, appointed in September under a contract to January 2029 covering more than 300 households, with implementation hoped for in January.

Members asked about climate change, future rainfall and sea-level rise, sediment washed from agricultural land and roads into drains and watercourses, coastal erosion, and whether flood infrastructure is designed for current risk or for 20, 30 or 50 years ahead. Officers pointed to the Broadland Futures Initiative, climate change uplifts in planning, and a review of the Local Flood Risk Management Strategy where maintenance and sediment wording is being strengthened. They said most watercourses are the responsibility of the Environment Agency and many roadside ditches are privately owned, with the council contacting landowners where ditches are silted.

Members also asked about gully cleansing capacity, highway drainage — officers said about £1.5m a year is spent on revenue drainage cleansing and about £3m on capital drainage improvements — and surface dressing leaving gullies blocked by stone and leaves. Officers said sweeping usually returns about a week after dressing and that the point would be fed back. Members raised the process for feeding back on Anglian Water's drought plan and flood incident reduction plan, both due for renewal in 2027, and officers said Anglian Water would return to the committee in early 2027.

Forward Work Programme

The committee agreed its Forward Work Programme, including bringing the highways performance report forward from March to the 14 January 2027 meeting to align with departmental timescales, and moving the follow-up scrutiny of Anglian Water to 11 March 2027. Councillor Rob Colwell asked for consideration of a 28 March 2023 Full Council motion on rights of rivers, which had been referred to this committee, to be added to the programme; the Chair said it could be considered offline following the meeting.


  1. The Medium Term Financial Strategy (MTFS) is the council's multi-year financial plan, setting out expected income, spending pressures and savings needed over several years. ↩

  2. The referendum threshold is the level of council tax increase above which a council must hold a local referendum, set by central government. ↩

  3. An equality impact assessment (EqIA) is an assessment of how a proposal may affect people with protected characteristics under the Equality Act 2010, and what mitigating actions are needed. ↩

  4. Active Travel England is the government's executive agency responsible for making walking, wheeling and cycling the preferred choice for everyday journeys in England, and for allocating the Active Travel Fund. ↩

  5. Highway Code Rule 140 states that you must not drive or park in a cycle lane marked by a solid white line during its times of operation, with limited exceptions. ↩

  6. A stage 3 road safety audit is a post-construction audit of a highway scheme, checking road, pavement and junction safety and identifying remedial works. ↩

  7. A 1% annual probability event is an event with a 1 in 100 chance of occurring in any given year. ↩

  8. The Lead Local Flood Authority (LLFA) is the county council's statutory role for managing local flood risk from surface water, ordinary watercourses and groundwater, and for developing a local flood risk management strategy. ↩

Attendees

No attendees have been recorded for this meeting.

Topics

Active Travel England Anglian Water Suffolk County Council Norfolk County Council's budget proposals for 2027-28 Local Flood Risk Management Strategy Director of Democratic and Regulatory Services Section 151 officer Environment Agency Internal Drainage Boards Local Transport Consolidated Funding Settlement Director of Strategic Finance Norfolk County Council Local Transport Plan Bus Service Improvement Plan Planning Obligations Standards Flood Risk Active Travel Saham Toney Flood Alleviation Scheme Dereham Flood Management Scheme Lead Director - Infrastructure Head of Sustainable Transport Reclaim the Rain programme Middleton Road / Church Lane Active Travel scheme Jellicoe Road Active Travel scheme Councillor

Meeting Documents

Agenda

261112 Infrastructure and Development Select Committee Agenda

Additional Documents

261112 - final list of Public and Local Member questions and responses