Subscribe to updates

You'll receive weekly summaries about Norwich Council every week.

If you have any requests or comments please let us know at community@opencouncil.network. We can also provide custom updates on particular topics across councils.

Audit committee - Tuesday, 10 November 2026

November 10, 2026 at 4:30 pm View on council website  Watch video of meeting Read transcript (Professional subscription required)

Chat with this meeting

Subscribe to our professional plan to ask questions about this meeting.

“What historic accounting gaps will disclaim 2025-26 accounts?”

Subscribe to chat
AI Generated

Summary

Open Council Network is an independent organisation. We report on Norwich and are not the council. About us

Norwich City Council's Audit Committee met on 10 November 2026 to consider the 2025-26 Statement of Accounts, which external auditor Ernst & Young expects to disclaim for a historical reason while giving more assurance than in previous years, alongside a continuing significant weakness in governance of council companies including the former Lion Homes. The committee also noted internal audit work, a quarterly corporate risk register with two new risks, and in private session the terms of reference for a Lion Homes lessons learned review, with final signing of the accounts and constitution changes on subsidiaries still to come later in November.

Statement of Accounts 2025-26 and Annual Governance Statement

The committee considered the 2025-26 Statement of Accounts and the Annual Governance Statement, which the report recommended it approve and delegate to the Acting Director of Finance (S151 Officer) and the Chair to make minor changes and sign the accounts once the audit is concluded in November.

Acting Director of Finance Robert Mayes told the committee the draft accounts had been published on 30 June 2026, before the statutory deadline, and that the public inspection period and audit had been completed in time for the 31 January 2027 backstop. He said this was an improvement on 2024-25, when the accounts had not been signed by March, and put the council in a better position for the earlier deadline that will apply from 2026-27.

External auditor David Riglar of Ernst & Young said the Provisional Audit Results Report was provisional while outstanding procedures were finished, but that he expected a disclaimer of opinion. He stressed this was not because EY had no assurance over the current year, as it had completed all planned procedures for 2025-26 for the first time in about four years, but because of historic gaps in balances carried forward from earlier disclaimed years.

The Audit Results Report said assurance had improved in 11 areas, with remaining gaps mainly in Property, Plant and Equipment, Revenue Grants Received in Advance and Reserves. The readiness assessment showed only one of eight indicators as requires improvement – the volume and value of identified misstatements – compared with only two indicators in the effective bracket for 2024-25.

Mr Riglar said a return to an unqualified opinion was anticipated by 2028-29 under the government's rebuilding assurance programme, but would require work to rebuild assurance over historic records going back three to four years, including testing samples from the disclaimer years where balances were significant.

On Value for Money, EY reported one remaining significant weakness, concerning governance of subsidiaries. The earlier weakness on timely financial reporting was no longer reported, following publication on time and better working papers.

The committee discussed a single unadjusted judgemental difference of £1.5 million in property valuations, arising from a disagreement between the council's valuers NPS and EY's valuers on notional acquisition and disposal costs. Members were asked to approve that difference in the Letter of Representation. The accounts also included adjustments to council dwellings, a bad debt provision for Private Sector Leasing, and pension figures, and a restatement of the 2024-25 group accounts for Norwich City Services Ltd to align with accounts filed at Companies House.

Members asked what evidence would show the new subsidiary governance framework was operating effectively, not just written down. Officers said constitutional amendments, a revised Shareholder Panel terms of reference, shareholder agreements and company articles were being taken through the Constitution Working Group, Cabinet and then Full Council in November, with the aim of having arrangements in place by January. The revised panel would include the Chairs of the Audit and Scrutiny Committees and an observer.

One councillor asked for a recommendation to the Constitution Working Group for a binding schedule of meetings and reporting for subsidiary companies to ensure the previous situation, where the Shareholder Panel did not meet for a year, did not recur.

Members also asked who had been external auditor in 2015 to 2020, when EY now says adequate oversight arrangements for Lion Homes appear never to have existed since its incorporation in November 2015, and why the issue was not picked up earlier. Officers said there had been no formal audit from 2020, that 2024-25 was the first audit capturing that period, and undertook to provide a written response on the 2015-20 position and on what the inappropriate operating practices and emerging challenges referred to in the EY report were. Another member noted internal audit had systematically flagged governance weaknesses at the time, and that senior officers and Cabinet were aware, but action had not been taken as necessary.

On the Annual Governance Statement, officers proposed changing wording on pages 266 and 364 of the pack, replacing candid with rather than describing governance arrangements in a sentence about emphasising governance judgements.

Governance of Lion Homes and other companies

Much of the discussion concerned Lion Homes (Norwich) Ltd, a wholly council-owned company set up in 2015 to develop affordable and market housing, which entered a Members' Voluntary Liquidation 1 in 2025 and is expected to enter formal liquidation shortly after the council's £6.15 million loan was impaired to nil.

EY's provisional report said the council did not have effective policies, procedures or governance arrangements for overseeing part-owned and wholly owned subsidiaries, that its constitution referenced only one subsidiary and imposed no reporting duties, and that members and officers were unaware of inappropriate practices and emerging challenges in one subsidiary because its board and the Shareholder Panel had only minimal engagement requirements.

EY said the significant weakness remained for 2025-26 because the constitutional amendments, lessons learned review and a comprehensive sustainable framework were not finalised, approved or operating effectively by 31 March 2026, and because the March 2026 findings left little time before the year end. Officers accepted the timing point, saying work had been underway since an informal briefing to the committee in January 2026 and that a separate Lion Homes lessons learned report would be considered under exempt business.

Members asked about risks to other companies, including Norwich City Services Ltd (NCSL), which provides environmental and building repairs services, and AS Regen LLP, the joint venture with Aviva Capital Partners Ltd for Anglia Square regeneration, while governance improvements were still being enacted. Officers said a review of the whole company governance framework covering all companies and the joint venture was underway.

Internal Audit progress

Head of Internal Audit Teresa Sharman reported progress on the 2026-27 Internal Audit Plan. There had been no changes to the plan and no audits deferred or cancelled, although one audit was behind schedule, which she said meant behind its agreed timetable rather than stopped, with a draft report now received. Counter Fraud was confirmed as on track, correcting the summary chart.

Four final reports were issued in the quarter covered: Pride in Place Governance received Substantial assurance, while Emergency Planning and Business Continuity, HR Pre-Employment Checks, and Data Retention and Disposal each received Limited assurance 2. Members noted the public summary identified those three limited areas and asked whether three limited opinions in one quarter suggested underlying corporate issues. Ms Sharman said timing explained the grouping, that themes across the reports would be discussed in the confidential section, and that three limited opinions across a year was not in itself significant.

The report said 40 of 52 recommendations from 2025-26 were complete, with 11 recommendations past their due date overall. A gap analysis against the Global Internal Audit Standards showed full conformance with 33 of 52 standards and partial conformance with 19, with an external quality assessment due in 2027 and work planned on an engagement plan and a standalone internal audit strategy.

Members asked at what point repeated slippage on an audit became a corporate governance issue for escalation to the Executive Leadership Team or the committee. Ms Sharman said escalation would happen after weekly meetings with the client, first to the Director of Finance, and not at the current stage where information was arriving, albeit in dribs.

Pre-employment and DBS checks were raised as a concern. The outstanding recommendations list showed urgent actions past their due date on ensuring all data fields in Unit 4 and manual records were completed and on providing a progress report to the Executive Leadership Team and Assurance Board, with officers saying work was underway as a manual process and DBS compliance was being incorporated into quarterly reporting.

Corporate Risk Register – Quarter 2

The committee noted the Corporate Risk Register for quarter two 2026-27. Officers said two risks were new or escalated: CORP38E on Local Government Reorganisation uncertainty during the pause, replacing four earlier LGR risks after the government withdrew its March 2026 decision to create three unitary councils in Norfolk, and CORP39 on serious fire or structural failure in higher-risk buildings, escalated from the Communities and Housing directorate.

For CORP39, named in the meeting as CORP39 in discussion, officers said likelihood had not changed but impact had been increased from 4 to 5 to reflect a fatality or life-changing injury, in line with the council's risk policy scoring a fatality as 5. Members welcomed its inclusion after the Grenfell Tower fire and asked why it had become an elevated risk now, and officers said the council was investing in buildings and working with Norfolk Fire and Rescue Service.

CORP06 on failure to respond to a critical business continuity event had worsened from 12 to 16, following the limited assurance internal audit on Emergency Planning and Business Continuity and national preparedness guidance for winter. CORP09 on Anglia Square improved from 15 to 12 as the remaining financial risk fell as demolition and site works progressed. CORP21 on climate change remained at 20.

Members asked about CORP38E, which was numbered CORP38 in discussion. Officers said it amalgamated staffing, finance, business as usual and new council risks, capturing uncertainty about how long to maintain business as usual, whether to retain capacity built up for LGR, and how to hold reserves for any future reorganisation. Earlier in the accounts discussion officers had said there was no specific LGR reserve, but money had been moved into reserves and a specific reserve was being considered.

On risk appetite, officers said it was a guide, not an absolute benchmark, and risks outside it were reported by exception so members could focus on them. Four public risks – CORP03 on health and safety, CORP06, CORP21 and CORP39 – had target scores outside risk appetite, with explanations that some risks could not fully be reduced, including the global nature of climate change. A review with the Good Governance Institute, which helped develop the risk strategy a year ago, was planned to survey risk owners and review risk appetite scoring.

Work Programme and other items

The committee considered the Work Programme for 2026-27, including standing items on internal and external audit, the risk register, the Statement of Accounts and Annual Governance Statement in January, and items to be added on the Local Code of Corporate Governance, CIPFA Code of Financial Management and self-assessment, Artificial Intelligence, and the Transparency and Information audit. Action tracker items included a yearly staff survey on risk management and risk appetite, an annual fraud report, and training on the Audit and Risk Universe before January 2027.

In exempt session, the agenda listed the exempt appendix to the Corporate Risk Register and the Lion Homes Lessons Learned Review Terms of Reference, both withheld on grounds relating to the financial or business affairs of a particular person under Paragraph 3 of Schedule 12A to the Local Government Act 1972 3.

For further information, see the Agenda Document Pack - Audit committee - 10/11/2026 and the Agenda Contents. The meeting was held in the Mancroft Room, City Hall, Norwich.


  1. Members' Voluntary Liquidation is a formal process to close a solvent company, pay its debts and distribute any remaining assets to shareholders. Lion Homes' accounts have been prepared on a break-up basis rather than as a going concern because it cannot repay its loan and is being wound up. ↩

  2. Substantial assurance means a robust system of internal controls; Reasonable means generally adequate but some improvements needed; Limited means generally inadequate or not operating effectively and significant improvements are required; No Assurance means a fundamental breakdown of core controls. ↩

  3. Schedule 12A Paragraph 3 covers information relating to the financial or business affairs of any particular person, including the authority holding the information, which can justify holding a meeting in private where the public interest in maintaining the exemption outweighs the public interest in disclosure. ↩

Attendees

No attendees have been recorded for this meeting.

Topics

Annual Governance Statement Corporate Risk Register Local Code of Corporate Governance Transparency and Information audit Value for Money Climate Change Statement of Accounts 2025-26 including Annual Governance Statement 2025-26 CIPFA Financial Management Code governance of council companies risk appetite Lion Homes Lessons Learned Review Anglia Square regeneration Lion Homes AS Regen LLP NPS Norwich City Services Ltd Ernst & Young Aviva Capital Partners Ltd Acting Director of Finance Chair Head of Internal Audit Local Government Reorganisation

Meeting Documents

Agenda

Agenda Contents

Reports Pack

Agenda Document Pack - Audit committee - 10/11/2026

Additional Documents

Appendix A - 2025-26 Statement of Accounts
Progress Report 2026-27
Corporate Risk Register - Appendix B (Public)
Statement of Accounts 2025-26
Appendix C – Management action plan in response to the ARR
Appendix D – Annual Governance Statement (AGS)
Corporate Risk Register 2026-27 – Quarter 2
Appendix B – Norwich City Council, Audit Results Report Year ended 31 March 2026
Audit Committee September minutes