Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm
The Cabinet Procurement and Insourcing Committee (CPIC) convened to discuss and approve several key contracts, including the refurbishment of the Kings Hall Leisure Centre (KHLC), park play area upgrades, security services, Google Workspace licences, additional resources for Stoke Newington School, and penalty charge notice enforcement agent services. The committee approved all recommendations put before it.
Cabinet Procurement and Insourcing Committee - Monday 6 October 2025 2.00 pm
The Cabinet Procurement and Insourcing Committee met on 6 October 2025, and approved the procurement of Google Workspace licences, planned internal and external works, communal works, and void works. The committee also noted the minutes of the Hackney Procurement Board meeting held on 8 July 2025, and approved the minutes of the Cabinet Procurement and Insourcing Committee held on 1 September 2025.
Cabinet Procurement and Insourcing Committee - Monday 1 September 2025 2.00 pm
The Cabinet Procurement and Insourcing Committee met on 1 September 2025, and made decisions on supported living services, and disabled facilities grants. The committee also discussed a council housing acquisition programme, but deferred a decision on it.
Cabinet Procurement and Insourcing Committee - Monday 7 July 2025 2.00 pm
The Cabinet Procurement and Insourcing Committee was scheduled to discuss several contract awards and procurement strategies, including those related to children's services, decarbonisation, cycle hire, fire safety, and housing. The committee was also expected to review the terms of reference for the committee, and minutes from previous meetings of the Hackney Procurement Board and the Cabinet Procurement and Insourcing Committee.
Extra-ordinary, Scrutiny Panel - Thursday 12 June 2025 7.00 pm
The Hackney Council Scrutiny Panel met to discuss the Housing Ombudsman's Special Report on Hackney Council, which highlighted several areas of service failure, including repairs, damp and mould, and complaint handling. The panel also established a Budget Scrutiny Task and Finish Panel to review the council's budget and ensure it aligns with strategic objectives and community priorities.
Decisions from Meetings
83 decisions · Page 1 of 17
F S650 Security Services Contract - Lots 1 & 2, Hackney Corporate Site Security, Vacant Buildings and Concierge Services
From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025
...to award framework agreements for four years to Supplier C for both Lot 1, providing security services, and Lot 2, providing concierge services, to the Council.
For Determination
F S624 Google Workspace Licences - Contract Award
From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025
...to ensure the continuity of essential services, they approved the award of a contract to Supplier C for the supply of Google Workspace licenses for an initial two-year term, with a one-year extension option.
For Determination
HCE S653 Kings Hall Leisure Centre (KHLC) Refurbishment Project - Enabling Works Design and Build contract award and Main Works Design and Build (D&B) Contract Award
From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025
...the committee approved the award of a JCT Design and Build Enabling Works contract and a JCT Design and Build Main Works contract to Morgan Sindall for the Kings Hall Leisure Centre Refurbishment Project, subject to Cabinet approval of the revised project budget.
For Determination
HCE S603 Parks Play Areas Refurbishments Phase 3: Design and Build Contract
From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025
...to award a JCT Design & Build contract for Phase 3 of the Play Area Refurbishment Programme to the most economically advantageous tenderer for £2,332,375, and to delegate authority to the Director Environment & Climate Change to finalize the contract.
For Determination
CE S640 Stoke Newington School - Creation of Additional Resourced Provision Assessment Centre and Media Suite Works
From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025
...to appoint Contractor C as the Design and Build Contractor for the Stoke Newington School project, which includes an Additional Resourced Provision for 30 pupils and a media suite, starting from RIBA Stage 3+ onwards.
For Determination
Summary
Meetings Attended: 18
Average per Month: 0.9
Decisions Recorded: 83